Reimagine Potrero Yard with Us
Potrero Yard, one of Muni’s oldest bus yards, is the first facility in the modernization and improvement project being proposed through the Building Progress Program . The SFMTA launched the Building...
L Taraval Improvement Project Work Forecast Oct. 21 - Nov.8, 2019
Work planned October 21 to November 8, 2019 Details of Work to be Performed: Continuation of sewer main replacement is planned for October 21-25, October 28-November 1, and November 4-8 between 45th...
Geary Rapid Project Construction Forecast: October 19, 2019 - November 1, 2019
As part of the Geary Rapid Project, work to replace aging water and sewer lines on Geary Boulevard, in coordination with San Francisco Public Utilities Commission, continues. Work to replace water...
Van Ness Avenue Construction Forecast: October 21, 2019 - November 1, 2019
Those traveling on the corridor are advised to stay alert and allow more travel time during construction. Polk Street, one block east of Van Ness Avenue, is a recommended alternative for people...
Van Ness BRT Community Advisory Committee Meeting Agenda - October 24, 2019
Potrero Yard Modernization Project Working Group Meeting Minutes #6
Potrero Yard Modernization Project Working Group Meeting Minutes #7
Potrero Yard Modernization Project Working Group Meeting Presentation # 6
Update on Parking Control Officers at West Portal
Since earlier this year, Parking Control Officers (PCO's) have been stationed at the West Portal and Ulloa intersection to help direct traffic. In general, this helped keep things moving and made sure...
Central Subway Construction Update 10/2/15
Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...
Letter: TBM Extraction Alternatives 11/16/12
Dear Neighbor: We hope you can join us on Monday, November 19, for a community meeting about the Central Subway Project and construction activities in North Beach. In the months since our last public...
Central Subway Construction Update 7/8/16
Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...
Central Subway Construction Update 10/25/13
Construction Update October 25-November 4, 2013 During the next 10 days, tunneling and tunneling preparatory work will continue in SoMa, Union Square and North Beach. Work to prepare for station...
Central Subway Construction Update 12/7/18
Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...
Central Subway Construction Update 6/17/16
Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...
Central Subway Construction Update 6/28/13
Construction Update June 29-July 15, 2013 During the next 17 days, construction to prepare for tunneling will continue in SoMa and Union Square. In North Beach, Pagoda Palace demolition contractor MH...
Central Subway Construction Update 3/28/14
Construction Update March 29 - April 7, 2014 During the next 10 days, Central Subway work will continue at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates...
Central Subway Construction Update 11/15/13
Construction Update November 16-25, 2013 During the next 10 days, tunneling and tunneling preparatory work will continue in SoMa, Union Square and North Beach. Work to prepare for station construction...