Van Ness Improvement Project Construction Forecast: July 5 - July 16, 2021
Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit
Walking
|
|
|
Construction Forecast for July 6 to July 19, 2021
Those traveling on the corridor are advised to stay alert and allow more travel time during construction. Polk Street, one block east of Van Ness Avenue, is a recommended alternative for people traveling by bicycle in the area. At times, bus stops along Van Ness Avenue and its side streets need to be relocated to perform construction for the Van Ness Improvement Project. Signage directs riders to temporary stops.
Parking is currently not available on Van Ness Avenue due to construction. Drivers can find parking in private lots or on side streets. Please do not park on sidewalks or in live traffic lanes. This is dangerous and may result in citations. The work listed below is scheduled for daytimes, 7 a.m. to 8 p.m. Planned night work is italicized. The night shift for construction is 8 p.m. to 7 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work. The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess. In the next two weeks crews are scheduled to work on overhead power installations, traffic signal wiring and hardware installation, light pole setting and related work.
Tuesday through Friday, July 6 through July 9 (Crews will not be working on July 5) Traction power cable pull to be performed between Marina Boulevard and Laguna Street.
- Chestnut to Lombard. *Disruptive noise is expected.
- Lombard to Greenwich. *Disruptive noise is expected.
- Filbert to Union. *Disruptive noise is expected.
- Union to Green. *Disruptive noise is expected.
- Green to Vallejo. *Disruptive noise is expected.
- Vallejo to Broadway. *Disruptive noise is expected.
- Broadway to Pacific. *Disruptive noise is expected.
- Pacific to Jackson. *Disruptive noise is expected.
- Jackson to Washington. *Disruptive noise is expected.
- Washington to Clay. *Disruptive noise is expected.
- Clay to Sacramento. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Sacramento to California. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- California to Pine. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Pine to Bush. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Bush to Sutter. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Sutter to Post. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Geary to O'Farrell. *Disruptive noise is expected.
- O'Farrell to Ellis. *Disruptive noise is expected.
- Ellis to Eddy. *Disruptive noise is expected. Paving work at Eddy may close intersection at times.
- Eddy to Turk. *Disruptive noise is expected. Paving work at Eddy may close intersection at times.
- Turk to Golden Gate. *Disruptive noise is expected. Street base work at Golden Gate may close intersection at time.
- Golden Gate to McAllister. *Disruptive noise is expected. Paving work at McAllister and street base work at Golden Gate may close intersection at times.
- McAllister to Grove. *Disruptive noise is expected. Paving work at McAllister and street base work at Grove may close intersection at times.
- Grove to Hayes. *Disruptive noise is expected. Street base work at Grove may close intersection at time.
- Hayes to Fell. *Disruptive noise is expected. Street base work at Fell may close intersection at time.
- Fell to Market. *Disruptive noise is expected. Street base work at Fell may close intersection at time.
- Market to Mission. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
Monday through Friday, July 12 through July 16 Traction power cable pull to be performed between Marina Boulevard and Laguna Street.
- Bay to Francisco. *Disruptive noise is expected.
- Francisco to Chestnut. *Disruptive noise is expected
- Chestnut to Lombard. *Disruptive noise is expected.
- Lombard to Greenwich. *Disruptive noise is expected.
- Greenwich to Filbert. *Disruptive noise is expected.
- Filbert to Union. *Disruptive noise is expected.
- Union to Green. *Disruptive noise is expected.
- Green to Vallejo. *Disruptive noise is expected.
- Vallejo to Broadway. *Disruptive noise is expected.
- Broadway to Pacific. *Disruptive noise is expected.
- Pacific to Jackson. *Disruptive noise is expected.
- Jackson to Washington. *Disruptive noise is expected.
- Washington to Clay. *Disruptive noise is expected.
- Clay to Sacramento. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Sacramento to California. *Disruptive noise is expected.
- California to Pine. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Pine to Bush. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Bush to Sutter. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Sutter to Post. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Geary to O'Farrell. *Disruptive noise is expected.
- O'Farrell to Ellis. *Disruptive noise is expected.
- Ellis to Eddy. *Disruptive noise is expected.
- Eddy to Turk. *Disruptive noise is expected.
- Turk to Golden Gate. *Disruptive noise is expected. Street base work at Golden Gate may close intersection at time.
- Golden Gate to McAllister. *Disruptive noise is expected. Street base work at Golden Gate may close intersection at time.
- McAllister to Grove. *Disruptive noise is expected.
- Grove to Hayes. *Disruptive noise is expected.
- Hayes to Fell. *Disruptive noise is expected. Street base work at Fell may close intersection at time.
- Fell to Market. *Disruptive noise is expected. Street base work at Fell may close intersection at time.
- Market to Mission. *Disruptive noise is expected.
|
|
|