Those traveling on the corridor are advised to stay alert and allow more travel time during construction. Polk Street, one block east of Van Ness Avenue, is a recommended alternative for people traveling by bicycle in the area.
At times, bus stops along Van Ness Avenue and its side streets need to be relocated to perform construction for the Van Ness Improvement Project. Signage directs riders to temporary stops.
Parking is currently not available on Van Ness Avenue due to construction. Drivers can find parking in private lots or on side streets. Please do not park on sidewalks or in live traffic lanes. This is dangerous and may result in citations.
The work listed below is scheduled for daytimes, 7 a.m. to 8 p.m. Planned night work is italicized. The night shift for construction is 8 p.m. to 7 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.
The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit the Van Ness Improvement Project webpage (SFMTA.com/VanNess). In the next two weeks, crews are scheduled to work on traffic improvements, overhead power installations, traffic signal wiring & hardware installation, light pole setting, median island furnishings, sidewalk flatwork and related work at the following locations.
Monday through Friday, September 27 through October 1
- Bay to Francisco. *Disruptive noise is expected.
- Francisco to Chestnut. *Disruptive noise is expected.
- Lombard to Chestnut *Disruptive noise is expected.
- Greenwich to Filbert. *Disruptive noise is expected.
- Filbert to Union. *Disruptive noise is expected. Night work is scheduled Sunday night, September 26, through Friday between the hours of 8 p.m. and 7 a.m.
- Union to Green. *Disruptive noise is expected. Night work is scheduled Sunday night, September 26, through Friday between the hours of 8 p.m. and 7 a.m.
- Green to Vallejo. *Disruptive noise is expected.
- Vallejo to Broadway. *Disruptive noise is expected.
- Broadway to Pacific. *Disruptive noise is expected.
- Jackson to Washington. *Disruptive noise is expected.
- Washington to Clay. *Disruptive noise is expected.
- Clay to Sacramento. *Disruptive noise is expected.
- Sacramento to California. *Disruptive noise is expected.
- Sutter to Post. *Disruptive noise is expected.
- Post to Geary. *Disruptive noise is expected.
- Geary to O'Farrell. *Disruptive noise is expected.
- O'Farrell to Ellis. *Disruptive noise is expected.
- Ellis to Eddy. *Disruptive noise is expected.
- Eddy to Turk. *Disruptive noise is expected.
- Turk to Golden Gate. *Disruptive noise is expected.
- Golden Gate to McAllister. *Disruptive noise is expected.
- McAllister to Grove. *Disruptive noise is expected.
- Grove to Hayes. *Disruptive noise is expected.
- Hayes to Fell. *Disruptive noise is expected. Night work is scheduled Sunday night, September 26, through Friday between the hours of 8 p.m. and 7 a.m.
- Fell to Market. *Disruptive noise is expected. Night work is scheduled Sunday night, September 26, through Friday between the hours of 8 p.m. and 7 a.m.
- Market to Mission. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m.
Monday through Friday, October 4 through October 8
- Bay to Francisco. *Disruptive noise is expected.
- Francisco to Chestnut. *Disruptive noise is expected.
- Lombard to Chestnut *Disruptive noise is expected.
- Filbert to Union. *Disruptive noise is expected. Night work is scheduled Sunday night, October 3, through Thursday between the hours of 8 p.m. and 7 a.m.
- Union to Green. *Disruptive noise is expected. Night work is scheduled Sunday night, October 3, through Thursday between the hours of 8 p.m. and 7 a.m.
- Vallejo to Broadway. *Disruptive noise is expected.
- Broadway to Pacific. *Disruptive noise is expected.
- Jackson to Washington. *Disruptive noise is expected.
- Washington to Clay. *Disruptive noise is expected.
- Clay to Sacramento. *Disruptive noise is expected.
- Sacramento to California. *Disruptive noise is expected.
- California to Pine. *Disruptive noise is expected.
- Pine to Bush. *Disruptive noise is expected.
- Sutter to Post. *Disruptive noise is expected.
- Post to Geary. *Disruptive noise is expected.
- Geary to O'Farrell. *Disruptive noise is expected.
- O'Farrell to Ellis. *Disruptive noise is expected.
- Ellis to Eddy. *Disruptive noise is expected.
- Eddy to Turk. *Disruptive noise is expected.
- Turk to Golden Gate. *Disruptive noise is expected.
- Golden Gate to McAllister. *Disruptive noise is expected.
- Hayes to Fell. *Disruptive noise is expected. Night work is scheduled Sunday night, October 3, through Thursday between the hours of 8 p.m. and 7 a.m.
- Fell to Market. *Disruptive noise is expected. Night work is scheduled Sunday night, October 3, through Thursday between the hours of 8 p.m. and 7 a.m.
- Market to Mission. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8 p.m. and 7 a.m.