Search - site wide text search

Displaying 21101 - 21125 of 27452
Project update

Central Subway Construction Update 11/1/13

Construction Update November 2-11, 2013 During the next 10 days, tunneling and tunneling preparatory work will continue in SoMa, Union Square and North Beach. Work to prepare for station construction...

Project update

North Beach Utility Relocation 9/28/12

Construction Update North Beach Utility Relocation This week the contractor continued construction to replace a sewer manhole. Next week construction to relocate a water line will be underway, and the...

Project update

Central Subway Construction Update 3/14/14

Construction Update March 15 - 24, 2014 During the next 10 days, Central Subway work will continue at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates about...

Project update

Central Subway Construction Update 12/18/15

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Central Subway Construction Update 3/23/18

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Central Subway Construction Update 5/26/17

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Central Subway Construction Update 11/22/13

Construction Update November 23-December 9, 2013 During the next 17 days, tunneling and tunneling preparatory work will continue in SoMa, Union Square and North Beach. Work to prepare for station...

Project update

Central Subway Construction Update 3/1/19

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

North Beach Utility Relocation 8/17/12

Construction Update North Beach Utility Relocation Construction associated with the Central Subway tunnel is now underway in North Beach. To keep the North Beach community informed during the upcoming...

Project update

Central Subway Construction Update 3/16/18

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Central Subway Construction Update 5/19/17

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Central Subway Construction Update 5/15/15

Central SubwayProject Advancements May 16 - May 25, 2015 This section contains brief updates about recent construction activities and a look-ahead for what to expect in Southern SoMa, Northern SoMa...

Project update

Central Subway Construction Update 5/12/17

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Central Subway Construction Update 9/8/17

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

North Beach Utility Relocation 9/14/12

Construction Update North Beach Utility Relocation This week the contractor completed work to relocate an AT&T underground utility line. Construction on a city water line and a sewer manhole is...

Project update

Central Subway Construction Update 9/6/13

Construction Update September 7-16, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. In North Beach, demolition of the Pagoda Palace will...

Project update

Central Subway Construction Update 5/30/14

Construction Update May 31 - June 9, 2014 During the next 10 days, Central Subway work will continue at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates...

Project update

Central Subway Construction Update 6/5/15

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Central Subway Construction Update 5/2/14

Construction Update May 3 - May 12, 2014 During the next 10 days, Central Subway work will continue at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates about...

Project update

Central Subway Construction Update 11/18/16

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Letter: Planning Commission SUD 2/13/13

Dear Neighbor, As part of the process to relocate the retrieval site for the Central Subway's tunnel boring machines (TBMs), the Planning Commission will consider a Special Use District (SUD) for the...

Project update

Central Subway Construction Update 7/31/15

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Central Subway Construction Update 8/12/16

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...