The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.
The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.
Tentative schedule:
In the next two weeks crews are scheduled to work on sewer and water main installation, sidewalk replacement, installing a joint utility trench and street light conduits, and potholing for upcoming work.
Monday through Friday, January 7 through January 11
- Lombard to Greenwich. Night work is scheduled Friday, January 11, between the hours of 8:00 p.m. and 7:00 a.m. Disruptive noise is expected.
- Greenwich to Filbert. Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Filbert to Union. Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Union to Green. Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Green to Vallejo. Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Vallejo to Broadway. Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Broadway to Pacific. Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Washington to Clay. *Intensive noise and vibrations is expected
- Clay to Sacramento.
- Sacramento to California.
- California to Pine.
- Pine to Bush. (Thursday and Friday only)
- Bush to Sutter. (Thursday and Friday only)
- Sutter to Post. (Monday through Wednesday only)
- Post to Geary. (Monday through Wednesday only)
- Geary to O'Farrell. Note: Myrtle Street is scheduled to be closed for work Wednesday through Friday
- O'Farrell to Ellis. (Tuesday through Thursday only)
- Ellis to Eddy. (Tuesday through Thursday only)
- Eddy to Turk. (Tuesday through Friday only)
- Turk to Golden Gate. (Tuesday through Friday only)
- McAllister to Grove. (Tuesday through Friday only)
- Grove to Hayes. (Tuesday through Friday only)
- Hayes to Fell.
- Fell to Market.
Monday through Friday, January 14 through January 18
- Lombard to Greenwich. Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Greenwich to Filbert. Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Filbert to Union. Night work is also scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m.
- Union to Green.
- Green to Vallejo. (Monday and Tuesday only)
- Washington to Clay. (Monday through Wednesday only)
- Clay to Sacramento. (Monday through Wednesday only)
- Sacramento to California. *Intensive noise and vibrations is expected
- California to Pine. *Intensive noise and vibrations is expected
- Bush to Sutter.
- Geary to O'Farrell. Note: Myrtle Street is scheduled to be closed for work Monday and Tuesday
- Ellis to Eddy.
- Eddy to Turk.
- Turk to Golden Gate. (Monday and Tuesday only)
- Golden Gate to McAllister. Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- McAllister to Grove. Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Hayes to Fell.
- Fell to Market.
- Market to Mission.
*We are working on improving the format of our weekly construction forecasts. Please share your feedback with staff at VanNessBRT@SFMTA.com