The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit sfmta.com/vanness.
The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.
Tentative Schedule:
Northpoint to Bay: Friday, July 13, crews are scheduled to pothole for upcoming work.
Lombard: Thursday, July 12, and Friday, July 13, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.
Night work is scheduled Monday, July 2, through Tuesday, July 3, Thursday, July 5, through Friday July 6, and Monday July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer and water main installation. Disruptive noise is expected.
Union: Thursday, July 5, through Friday July 6, and Monday July 9, through Friday, July 13, crews are scheduled to work on water main installation.
Green to Vallejo: Monday, July 2, through Tuesday, July 3, Thursday, July 5, through Friday July 6, and Monday July 9, through Friday, July 13, crews are scheduled to work on roadway restoration.
Broadway to Pacific: Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, crews are scheduled to work on sewer and water main installation. Due to sewer work, intensive noise and vibration is expected.
Pacific to Jackson: Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Thursday, July 5, through Friday July 6, and Monday July 9, through Friday, July 13, crews are scheduled to work on water main installation.
Night work is scheduled Monday July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.
Jackson to Washington: Night work is scheduled Monday July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.
Washington to Clay: Night work is scheduled Monday July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.
Clay to Sacramento: Night work is scheduled Monday July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.
Sacramento to California: Night work is scheduled Monday July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.
California to Pine: Night work is scheduled Monday July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.
Pine to Bush: Night work is scheduled Monday July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.
Bush to Sutter: Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday, July 6, crews are scheduled to work on water main installation.
Night work is scheduled Monday July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.
Sutter to Post: Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday, July 6, crews are scheduled to work on water main installation.
Night work is scheduled Monday July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.
Post to Geary: Monday, July 2, through Tuesday, July 3, Thursday, July 5, through Friday July 6, and Monday July 9, through Friday, July 13, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, crews are also scheduled to work on water main installation.
Night work is scheduled Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation.
Geary to O'Farrell: Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, crews are scheduled to work on sewer and water main installation. Due to sewer work, intensive noise and vibration is expected. Monday July 9, through Friday, July 13, crews are scheduled to install a joint-utility trench and to pothole for upcoming work.
Night work is scheduled Monday, July 2, through Tuesday, July 3, Thursday, July 5, through Friday July 6, and Monday July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on updating the emergency firefighting water system. Disruptive noise is expected.
O’Farrell to Ellis: Monday, July 2, through Tuesday, July 3, Thursday, July 5, through Friday July 6, and Monday July 9, through Friday, July 13, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Monday, July 2, through Tuesday, July 3, and Thursday, July 5, through Friday July 6, crews are also scheduled to install a joint-utility trench and to pothole for upcoming work.
Ellis to Eddy: Monday, July 2, through Tuesday, July 3, Thursday, July 5, through Friday July 6, and Monday July 9, through Friday, July 13, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Crews are also scheduled to install a joint-utility trench and to pothole for upcoming work. Monday July 9, through Friday, July 13, crews are scheduled to work on roadway restoration.
Night work is scheduled Thursday, July 5, and Friday July 6, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation.
Eddy to Turk: Monday, July 2, through Tuesday, July 3, Thursday, July 5, through Friday July 6, and Monday July 9, through Friday, July 13, crews are scheduled to work on sewer main installation and on installing a joint utility trench. Due to sewer work, intensive noise and vibration is expected. Monday July 9, through Friday, July 13, crews are also scheduled to work on roadway restoration.
Night work is scheduled Thursday, July 5, and Friday July 6, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation. Night work is also scheduled Monday July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.
Turk to Golden Gate: Monday, July 2, through Tuesday, July 3, Thursday, July 5, through Friday July 6, and Monday July 9, through Friday, July 13, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Crews are also scheduled to work on roadway restoration, on updating the emergency firefighting water system, and on installing a joint-utility trench.
Night work is scheduled Monday July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.
Golden Gate to McAllister: Monday, July 2, through Tuesday, July 3, Thursday, July 5, through Friday July 6, and Monday July 9, through Friday July 13, crews are scheduled to work on roadway restoration.
Night work is scheduled Monday, July 2, through Tuesday, July 3, Thursday, July 5, through Friday July 6, and Monday July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.
McAllister to Grove: Thursday, July 12, northbound on Van Ness and South Van Ness avenues lanes between Mission and McAllister streets will shift to extend the southern construction zone south from Sutter to Mission streets.
Night work is scheduled Monday, July 2, through Tuesday, July 3, Thursday, July 5, through Friday July 6, and Monday July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.
Grove to Hayes: On Friday, July 6, the left turn on northbound Van Ness Avenue at Hayes will be permanently removed. Drivers are advised to take other routes and plan for extra time. (See item below.) Thursday, July 12, northbound lanes on Van Ness and South Van Ness avenues between Mission and McAllister streets will shift to extend the southern construction zone south from Sutter to Mission streets.
Night work is scheduled Monday, July 2, through Tuesday, July 3, Thursday, July 5, through Friday July 6, and Monday July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.
Hayes to Fell: On Friday, July 6, the left turn on northbound Van Ness Avenue at Hayes will be permanently removed. Drivers are advised to take other routes and plan for extra time. (See item below.) Thursday, July 12, northbound lanes on Van Ness and South Van Ness avenues between Mission and McAllister streets will shift to extend the southern construction zone south from Sutter to Mission streets.
Night work is scheduled Monday, July 2, through Tuesday, July 3, Thursday, July 5, through Friday July 6, and Monday July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.
Fell to Market: Thursday, July 12, northbound lanes on Van Ness and South Van Ness Avenues between Mission and McAllister streets will shift to extend the southern construction zone south on Van Ness and South Van Ness avenues from Sutter to Mission streets.
Night work is scheduled Monday, July 2, through Tuesday, July 3, Thursday, July 5, through Friday July 6, and Monday July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming sewer work.
Market to Mission: Thursday, July 12, northbound lanes on Van Ness and South Van Ness Avenues between Mission and McAllister will shift to extend the southern construction zone south from Sutter to Mission streets.
Night work is scheduled Monday, July 2, through Tuesday, July 3, Thursday, July 5, through Friday July 6, and Monday July 9, through Friday, July 13, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities and to prepare the area for upcoming sewer work.