Project update

Central Subway Construction Update 12/12/14

Project Advancements December 13 - December 22, 2014 During the next 10 days, Central Subway work continues at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief...

Project update

Central Subway Construction Update 2/26/16

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Central Subway Construction Update 1/2/15

Project Advancements January 3, 2015 - January 12, 2015 During the next 10 days, Central Subway construction work continues at sites in SoMa, Union Square, Chinatown and North Beach. This section...

Project update

Central Subway Construction Update 12/15/17

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Central Subway Construction Update 2/7/14

Construction Update February 8-17, 2014 During the next 10 days, Central Subway work will continue at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates about...

Project update

North Beach Community Meeting 11/5/12

Please join us for aCommunity Meetingon theCentral Subway Projecthosted bySupervisor David Chiu When: Monday, November 19 at 7:30 p.m. Where: Telegraph Hill NeighborhoodCenter Gymnasium555 Chestnut...

Project update

Central Subway Construction Update 12/8/17

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Central Subway Construction Update 6/16/17

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Central Subway Construction Update 5/11/18

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Central Subway Construction Update 6/1/18

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Central Subway Construction Update 7/15/16

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Central Subway Construction Update 8/2/13

Construction Update August 3-12, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. In North Beach, demolition of the Pagoda Palace will...

Project update

Central Subway Construction Update 12/5/14

Project Advancements December 6 - December 15, 2014 During the next 10 days, Central Subway work continues at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief...

Project update

Central Subway Construction Update 2/27/15

Central SubwayProject Advancements February 28 - March 9, 2015 This section contains brief updates about recent construction activities and a look-ahead for what to expect in Southern SoMa, Northern...

Project update

Central Subway Construction Update 3/1/13

Construction Update March 2-11, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. No Central Subway construction is planned to occur in...

Project update

Central Subway Construction Update 7/3/14

Construction Update July 04 - July 14, 2014 During the next 10 days, Central Subway work will continue at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates...

Project update

Central Subway Construction Update 12/9/16

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Central Subway Construction Update 8/11/17

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Letter: North Beach Meeting Summary 4/19/13

Dear Neighbor: Last week at our community meeting in North Beach, SFMTA Director of Transportation Edward D. Reiskin and the Central Subway team explained the construction plan for the Pagoda Palace...

Project update

Central Subway Construction Update 4/1/16

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Central Subway Construction Update 12/11/15

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Central Subway Construction Update 4/5/13

Construction Update April 6-15, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. No Central Subway construction is planned to occur in...

Project update

Central Subway Construction Update 10/16/15

Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line to...

Project update

Central Subway Construction Update 7/11/14

Construction Update July 12 - July 21, 2014 During the next 10 days, Central Subway work will continue at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates...

Project update

North Beach Utility Relocation 10/19/12

Construction Update North Beach Utility Relocation This week Central Subway crews continued sewer line construction in North Beach. Sewer work is planned to continue next week, and most of this week's...