This page has older content

Please see Related Projects on this page for current project information. See Travel & Transit Updates for current travel updates. We are keeping this page as a record of SFMTA service and outreach.

Van Ness Avenue Construction Forecast: August 20 - August 31, 2018

Share this:
Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit sfmta.com/vanness.

The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

Tentative Schedule:

Lombard to Greenwich: Monday through Friday, August 27 through August 31, crews are scheduled to work on sewer installation.

Greenwich to Filbert: Monday through Thursday, August 27 through August 30, crews are scheduled to pothole for upcoming work.

Filbert to Union: Monday through Wednesday, August 20 through August 22, crews are scheduled to perform water work. Friday, August 31, crews are scheduled to pothole for upcoming work.

Jackson to Washington: Tuesday through Thursday, August 28 through August 30, crews are scheduled to work on permitted sidewalk tree removal. Friday, August 24, crews are scheduled to prepare the area for upcoming work.

Night work is scheduled Monday through Wednesday, August 20 through August 23, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole and to prepare the area for upcoming work.

Washington to Clay: Thursday, August 23 and Friday, August 24, crews are scheduled to prepare the area for upcoming work. Monday, August 27 and Tuesday, August 28, crews are scheduled to work on permitted sidewalk tree removal.

Night work is scheduled Monday through Wednesday, August 20 through August 23, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole and to prepare the area for upcoming work.

Clay to Sacramento: Thursday, August 23 and Friday, August 24, crews are scheduled to prepare the area for upcoming sewer work. Monday, August 27 and Tuesday, August 28, crews are scheduled to work on permitted sidewalk tree removal.

Night work is scheduled Monday through Wednesday, August 20 through August 23, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole and to prepare the area for upcoming work.

Sacramento to California: Monday, August 27 and Tuesday, August 28, crews are scheduled to work on permitted sidewalk tree removal.

Night work is scheduled Monday through Wednesday, August 20 through August 23, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole and to prepare the area for upcoming work.

California to Pine: Night work is scheduled Monday through Wednesday, August 20 through August 23, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole and to prepare the area for upcoming work.

Pine to Bush: Night work is scheduled Monday through Wednesday, August 20 through August 23, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole and to prepare the area for upcoming work.

Bush to Sutter: Thursday, August 23, crews are scheduled to prepare the area for upcoming work.

Night work is scheduled Monday through Wednesday, August 20 through August 23, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to prepare the area for upcoming work.

Post to Geary Monday through Friday, August 20 through August 24, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Night work is scheduled Monday through Wednesday, August 20 through August 23, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.

Geary to O'Farrell: Monday through Friday, August 20 through August 24, crews are scheduled to work on sewer main installation. Disruptive noise is expected. Monday through Friday, August 20 through August 24, and Monday through Friday, August 27 through August 31, crews are scheduled to install a joint utility-trench.

Night work is scheduled Monday through Friday, August 20 through August 24, and Monday through Friday, August 27 through August 31, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on updating the emergency firefighting system. Disruptive noise is expected.

O'Farrell to Ellis: Tuesday through Friday, August 21 through August 24, and Monday through Friday, August 27 through August 31, crews are scheduled to install a joint-utility trench. Monday through Friday, August 27 through August 31, crews are also scheduled to work on sidewalk replacement.

Ellis to Eddy: Monday through Thursday, August 20 through August 24, crews are scheduled to work on sewer installation and to perform water work. Monday through Friday, August 20 through August 24, and Monday through Friday, August 27 through August 31, crews are scheduled to work on sidewalk replacement.

Eddy to Turk: Monday through Thursday, August 20 through August 24, crews are scheduled to work on sewer installation and to perform water work. Monday through Friday, August 20 through August 24, and Monday through Friday, August 27 through August 31, crews are scheduled to work on sidewalk replacement.

Night work is scheduled Monday through Friday, August 20 through August 24, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on updating the emergency firefighting system.

Turk to Golden Gate: Monday through Friday, August 20 through August 24, crews are scheduled to work on sidewalk replacement.

Night work is scheduled Monday through Friday, August 20 through August 24, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on updating the emergency firefighting system.

Golden Gate to McAllister: Monday through Friday, August 20, through August 24, and Monday through Friday, August 27 through August 31, crews are scheduled to work on sidewalk replacement and to pothole for upcoming work.

Night work is scheduled Monday through Friday, August 20 through August 24, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

McAllister to Grove: Monday through Friday, August 20 through August 24, and Monday through Friday, August 27 through August 31, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Monday through Friday, August 20 through August 24, crews are scheduled to pothole for upcoming work.

Night work is scheduled Monday through Friday, August 20 through August 24, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

Grove to Hayes: Monday through Friday, August 20 through August 24, and Monday through Friday, August 27 through August 31, crews are scheduled to work on sewer main installation and to pothole for upcoming work. Due to sewer work, intensive noise and vibration is expected. Monday through Friday, August 27 through August 31, crews are also scheduled to install a joint-utility trench.

Night work is scheduled Monday through Friday, August 20 through August 24, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

Hayes to Fell: Monday through Friday, August 20, through August 24, crews are scheduled to pothole for upcoming work. Monday through Friday, August 27 through August 31, crews are scheduled to work on sewer main installation and to install a joint utility trench. Due to sewer installation work, intensive noise and vibration is expected.

Night work is scheduled Monday through Friday, August 20 through August 24, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

Fell to Market: Monday through Friday, August 20, through August 24, crews are scheduled to pothole for upcoming work.

Night work is scheduled Monday through Friday, August 20 through August 24, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.

Market to Mission: Monday through Friday, August 20, through August 24, crews are scheduled to pothole for upcoming work.

Van Ness traffic lanes shifting on August 23

In the early hours of Thursday, August 23, traffic lanes on Van Ness Avenue, between Jackson and Sutter streets, will shift slightly in order to make room for construction. Drivers are advised to exercise extra caution when traveling on Van Ness.

New construction zones will be created and sidewalk fencing is expected to be installed on the east side of these blocks between Thursday, August 23, and Saturday, August 25.