In the coming weeks, work continues on water lines and sewer lines. Underground conduit work is being performed to power the new and existing streetlights and OCS poles. Curb ramp work continues with demolition and grading areas in preparation for construction of the new boarding ramps and to upgrade existing boarding ramps. Track work is expected to begin over the next few weeks starting with the rail assembly. The tracks along Taraval Street are being prepared for the initial removal and installation of new rails. Construction teams will be excavating and jackhammering pavement, which may cause vibrations. Materials are also being temporarily staged nearby. Dust control and housekeeping measures are in place at active construction and staging locations.
The inbound bus stop at Taraval and 15th has been relocated across the intersection until fall 2024.
General construction hours are Monday to Friday between 8:00 a.m. and 4:00 p.m. Construction schedules are subject to change. “No Parking” signs will be posted in construction and staging areas, and intersections may be closed to through traffic on Taraval Street.
Multiple agencies are performing infrastructure work in the area. This includes work by Public Works on 19th Avenue, Public Utilities Commission at Vicente and Wawona streets and PG&E along Taraval Street.
L Taraval Improvement Project – Segment B
Construction work is scheduled to be performed - April 24 to May 6, 2023
Saturday work on April 29 is denoted with an asterisk *
Taraval Street
17th Avenue: construct large manhole
19th to 20th avenues: sewer line work, construct sewer laterals
19th to 24th, 28th avenues: traffic signal work, underground conduit and underground signal crossing
21st, 22nd, 27th, 28th avenues: curb ramp work, demolishing and grading, constructing curb ramp
22nd avenue: traffic signal work: pole foundation in sidewalk/curb ramp, traffic signal pull box
25th to 29th avenues: water line work, excavate service laterals, perform service lateral changeovers, backfill service laterals (anticipated start 5/8)
29th to 33rd avenues: Waterline work, excavate service laterals, perform service lateral changeovers and connections, backfill service laterals
Ulloa Street
14th to Funston avenues: water line work, chlorinate and connect segments
Track Work
Wawona Street
21st to 23rd avenues: track assembly work, flash butt welding *
Taraval Street – Track Area
17th to 22nd avenues: initial cleaning of sewer lines
17th to 22nd avenues: sewer lining installation (anticipated start June 6)
28th to 31st avenues: Demo and grade trackway (anticipated start May 15)
Temporary staging locations
16th Avenue west side from Taraval to Ulloa streets
17th Avenue west side from Taraval to Santiago streets
17th Avenue east side from Taraval to Santiago streets
17th Avenue west side from Taraval to Ulloa streets
22nd Avenue west side from Taraval to Santiago streets
24th Avenue east side Taraval to Santiago streets
26th Avenue west side between Taraval and Ulloa streets
29th Avenue west side from Taraval to Santiago streets
Please sign up for email and SMS project updates on the project page