Construction Update
June 22-July 1, 2013
During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. In North Beach, Pagoda Palace demolition contractor MH Construction will perform surveys of the site. No Central Subway construction is planned in Chinatown.
For descriptions of construction impacts in each neighborhood, scroll down or click on the links below. We also post construction, traffic detour and Muni impact information on our project Google Map.
Construction impacts are planned to change at these locations by July 1:
- Northern SoMa (Market to Harrison): Two lanes of traffic will remain closed on 4th Street between Howard and Folsom, but the traffic configuration will change (details in the Northern SoMa section). Construction will be underway on Saturdays until further notice. On 4th Street between Market and Stevenson, the sidewalk and two traffic lanes will remain closed on the eastern side of the street.
- North Beach: Pagoda Palace demolition contractor MH Construction will perform surveys of 1731-1741 Powell Street. For more information about construction at this site, check out this construction notice. We will provide detailed information about construction impacts before demolition begins.
At these locations, current construction impacts are planned to continue until July 1:
- Southern SoMa (Harrison to King/Berry): Full closure of 4th Street between Harrison and Bryant will continue some evenings and weekends. Two lanes of traffic will remain open at all other times. Contact us at central.subway@sfmta.com if you have questions about the closure schedule. On Bryant Street at 5th Street, the left lane and several parking spaces will remain closed.
- Union Square: Stockton Street between Geary and Ellis will remain closed to vehicle traffic. Ellis Street between Stockton and Powell will remain closed to westbound traffic.
- Chinatown: No construction planned
We appreciate your patience and support while we build this essential upgrade to San Francisco's public transportation system.
-The Central Subway Team
Crews are assembling the 350-foot-long machine underneath 4th Street. Southern SoMa
4th Street from Harrison to King/Berry
On 4th Street between Harrison and Bryant streets, the contractor has constructed a major excavation known as a launch box at the site where tunneling will begin. After assembly of a tunnel boring machine underground, tunneling will start this summer.
Planned construction:
- Install gantry crane inside launch box
- Test and commission TBM
- Launch TBM (tentative)
Traffic and pedestrian impacts:
- The two lanes on the east side of the street (left lanes for southbound traffic) will remain open to vehicle traffic except as described below.
- The block may close to traffic from 8 p.m. to 5:30 a.m. on weeknights and all day Saturday and Sunday. When the Giants have home games, the closure will start an hour after the game ends.
- The sidewalk on the west side of the block will remain closed; the sidewalk on the east side of the block will remain open.
- On Bryant Street at 5th Street, the left lane and several parking spaces will be closed.
Traffic and pedestrian controls are in place. For more information on construction impacts at this site, check out this blog post.
At 4th and Market, we have installed pipes that will be used to inject grout underground, improving soil conditions for when the tunnel boring machines pass below. Northern SoMa
4th Street from Market to Harrison
On 4th Street between Howard and Folsom streets, the contractor has constructed below-ground walls, called headwalls, at the site of the future Yerba Buena/Moscone Station. Ground improvement work (jet grouting) is also in progress. For more information on construction at this site, check out this blog post.
In addition, the contractor is performing ground improvement work (installation of compensation grout tubes) on 4th Street between Market and Stevenson. More information is available in this construction notice.
Planned construction (Market to Stevenson):
- Perform ground improvements
Traffic and pedestrian impacts (Market to Stevenson):
- Two lanes on the eastern side of the street (near Ross) will be closed
- The sidewalk on the eastern side of the street will be closed. A protected pedestrian walkway will be in place around the construction zone.
Planned construction (Howard to Folsom):
- Perform ground improvements on the western side of block
- Move construction zone from western to eastern side of block
- Perform ground improvements on the eastern side of the block
- Construction will be underway on Saturdays from 6 a.m. to 6 p.m.
Traffic and pedestrian impacts (Howard to Folsom):
- At least two lanes of traffic on 4th Street will remain open on the eastern side of the block (left lanes) until the middle of next week
- Starting next Wednesday, June 26, the traffic configuration may change, with two lanes open on the western side of the street (right lanes)
- The sidewalk on the western side of the street may be narrowed to facilitate construction. Pedestrian protections will be in place.
On Stockton Street, we are using these machines to build underground walls. Union Square
Stockton Street from Market to Post
On Stockton Street between Geary and Ellis streets, the contractor is installing below-ground walls called headwalls at the site of the future Union Square/Market Street Station. In addition, ground improvement is underway on Ellis Street between Stockton and Powell streets.
Planned construction:
- Construct headwalls on Stockton Street between Ellis and O'Farrell
- Mobilize headwall equipment and install headwalls on Stockton Street between O'Farrell and Geary
- Perform ground improvements on Stockton Street between O'Farrell and Geary
- Install ground improvement pipes in Ellis Street shaft
- The contractor will continue working two shifts on weekdays, from 6 a.m. to 12:30 a.m.
- On Saturdays, work hours will be 6 a.m. to 11:30 p.m.
Traffic, transit and pedestrian impacts:
- Stockton Street between Geary and Ellis is closed to all vehicles except emergency vehicles
- Ellis Street between Stockton and the Ellis-O'Farrell Garage (between Stockton and Powell) is closed to westbound traffic
- The 38/38L Geary may experience delays around Union Square
- Sidewalks on Stockton Street between Ellis and Geary will remain open, but they may be narrowed to facilitate construction
More information about construction at this site is available in this construction notice and this press release.
This property on Washington Street is the future location of the Chinatown Station. Chinatown
Stockton Street from Sacramento to Broadway
No construction is planned to occur in Chinatown during the next 10 days.
The Central Subway tunnel will end at this site in North Beach, now home to the old Pagoda Palace theater. North Beach
Columbus Avenue from Union to Filbert
On private property at 1731-1741 Powell Street, the contractor is preparing to construct a walled excavation known as a retrieval shaft at the site where tunneling will end. The two tunnel boring machines will be removed from the ground at this location.
Demolition of the building on the site will begin in July. Check out this construction notice for more details.
Planned construction:
- Demolition contractor MH Construction will perform surveys of the property
Traffic, transit and pedestrian impacts:
- None
- Prior to building demolition, we will provide detailed information about construction impacts in this email update and on our blog (www.centralsubwayblog.com)
Central Subway Construction Fast Facts
Project Alignment: 4th Street between Berry and Market streets; Stockton Street between Market Street and Columbus Avenue; Columbus Avenue between Stockton and Filbert streets.
Transit Reroutes: The southbound 8X/8AX/8BX Bayshore Express, 30 Stockton, 45 Union/Stockton and 91 Owl Muni bus routes have been rerouted to accommodate construction in Union Square and SoMa. These reroutes will remain in effect throughout the duration of Central Subway construction. More information is available online here.
Contact Us: Should you have questions about construction or the Central Subway Project, don't hesitate to contact our team. You can reach us at central.subway@sfmta.com or by phone at 415-701-4371.
For More Information: The Central Subway team posts frequent project updates on a variety of social media outlets. To find out more about the project and construction progress, follow us on Facebook, Twitter, Instagram or Flickr, and check out our blog.
Construction schedules are subject to change.