The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.
The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.
Tentative schedule:
In the next two weeks crews are scheduled to work on sewer and water main installation, sidewalk replacement, installing a joint utility trench and street light conduits, and potholing for upcoming work.
Wednesday through Friday, December 26 through December 28
- Green to Vallejo Night work is scheduled Friday, December 28, between the hours of 8:00 p.m. and 7:00 a.m.
- Vallejo to Broadway Night work is scheduled Wednesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Pacific to Jackson
- Jackson to Washington
- Washington to Clay
- Clay to Sacramento
- Sacramento to California
- California to Pine
- Pine to Bush
- Sutter to Post Night work is scheduled Wednesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Post to Geary Night work is scheduled Wednesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- O'Farrell to Ellis
- Ellis to Eddy
- Grove to Hayes (Wednesday and Thursday only)
- Hayes to Fell
- Fell to Market (Friday only)
Wednesday through Friday, January 2 through January 4
- Filbert to Union
- Union to Green
- Green to Vallejo Night work is scheduled Wednesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Vallejo to Broadway
- Washington to Clay
- Clay to Sacramento
- Sacramento to California
- California to Pine *Intensive noise and vibration is expected.
- Geary to O'Farrell
- Ellis to Eddy
- Eddy to Turk
- Turk to Golden Gate
- Hayes to Fell
- Fell to Market
*We are working on improving the format of our weekly construction forecasts. Please share your feedback with staff at VanNessBRT@SFMTA.com