April 1st, 8th and 15th 2023: Saturday work is scheduled between 8 a.m. and 4:30 p.m. on 15th, 17th, 18th, 20th and 21st avenues between Ulloa and Taraval
L Taraval Improvement Forecast and Project Segment B Update - March 27 - April 8, 2023
In the coming weeks, work continues on water and sewer lines, as well as on the overhead contact system (OCS) that powers the trains. OCS work is now focused on foundation work to prepare for the installation of new poles. Construction teams will be excavating and jackhammering pavement, which may cause vibrations. Materials are also being temporarily staged nearby. Dust control and housekeeping measures are in place at active construction and staging locations. Extreme weather conditions have impacted the construction schedule.
The inbound bus stop at Taraval and 15th has been relocated across the intersection until fall 2024.
General construction hours are Monday to Friday between 8:00 a.m. and 4:00 p.m. Construction schedules are subject to change. “No Parking” signs will be posted in construction and staging areas, and intersections may be closed to through traffic on Taraval Street. Please note that work hours are being temporarily extended during the week and there is upcoming weekend work scheduled. Construction work will be extended until 6:30 p.m. until March 31. Saturday work is scheduled for April 1.
Multiple agencies are performing infrastructure work in the area. This includes work by Public Works on 19th Avenue, Public Utilities Commission at Vicente and Wawona streets and PG&E along Taraval Street.
L Taraval Improvement Project – Segment B
Construction work is scheduled to be performed - March 27 - April 8, 2023
Saturday work is denoted with an asterisk *
Taraval Street
16th Avenue: water line work, segment connection
17th, 18th, 19th avenues: demolish and construct large sewer main, intersection water line work
22nd to 23rd avenues: OCS foundation and pole work
25th to 26th avenues: waterline work*
29th Avenue: excavate and shore, construct underground traffic signal
29th to 33rd avenues: water line work, excavating and shoring service laterals, backfill
28th, 29th, 30th, 33rd and 34th avenues: OCS foundation and pole work
33rd, 34th to 35th avenues: demolish and grade curb ramp, construct sidewalk and curb ramp
Ulloa Street
14th to 15th avenues: water line work, excavating and shoring
14th to Funston avenues: water line work, chlorinate and connect segments
14th Avenue and Ulloa Street: OCS foundation work
Temporary staging locations
16th Avenue west side from Taraval to Ulloa streets
17th Avenue west side from Taraval to Santiago streets
17th Avenue west side from Taraval to Ulloa streets
22nd Avenue west side from Taraval to Santiago streets
26th Avenue east side from Taraval to Santiago streets
28th Avenue east side from Taraval to Ulloa streets
Sign up for email and SMS project updates on the project page.