This page has older content

Please see Related Projects on this page for current project information. See Travel & Transit Updates for current travel updates. We are keeping this page as a record of SFMTA service and outreach.

L Taraval Improvement Project Work Forecast Dec. 2 - 13, 2019

Share this:
Neighborhoods Affected

Work Forecast Plan for the Weeks of December 2 to December 13, 2019.

 

Details of Work Performed:
  • Continuation of sewer main replacement is planned for the weeks of December 2-6 and December 9-13 between 44th and 43rd Avenue, and 40th and 37th Avenue.
  • Water line work is planned for the week of December 2-6 and December 9-13 between 46th and 44th Avenue. 
What to Expect:

Excavation requires jackhammering of the pavement. Dust control measures will be in place to prevent dust kick up from the work.

Heavy vibrations from the shoring and sheet piling work is expected for the entire duration of sewer main replacement.

Water line work is not expected to interrupt or shut off water service. 

Location and Time of Work:
  • Northside of Taraval Street between 46th - 43rd Avenue and 40th Avenue - 37th Avenue
  • Monday to Friday, 7:00a.m. to 5:00p.m.
Traffic Impacts: Some parking will be temporarily restricted in construction zones and traffic lanes will be modified in the northbound lane during active work. 
Muni Customer Impacts: None

The following two-week construction forecast is subject to change due to weather delays or unexpected field conditions.

Questions or concerns? Contact us at LTaravalProject@SFMTA.com or 415.646.2382

To view a map of temporary bus stop relocations citywide, please visit: SFMTA.com/TempStopMap

Stay Up To Date: For L Taraval Improvement Project work forecast and updates, please sign-up for email updates by visiting LTaravalProject/SFMTA.com.