The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit sfmta.com/vanness.
The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.
Tentative Schedule:
Lombard to Greenwich: Monday through Wednesday, July 16 through July 18, crews are scheduled to work on permitted sidewalk tree stump removal. Monday through Friday, July 23 through July 27, crews are scheduled to work on sewer main installation.
Night work is scheduled Monday through Friday, July 16 through July 20, and Monday through Friday, July 23 through July 27, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Disruptive noise is expected. Also on Tuesday through Thursday, July 17 through July 19, between the hours of 8:00 p.m. and 7:00 a.m., crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.
Greenwich to Filbert: Monday through Wednesday, July 16 through July 18, crews are scheduled to complete permitted sidewalk tree stump removal.
Night work is scheduled Monday through Thursday, July 16 through July 19, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.
Filbert to Union: Monday through Friday, July 16 through July 20, crews are scheduled to work on water main installation and permitted sidewalk tree stump removal.
Night work is scheduled Monday through Thursday, July 16 through 19, and Monday and Tuesday, July 23 and July 24, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.
Union to Green: Monday through Friday, July 16 through July 20, crews are scheduled to work on water main installation and permitted sidewalk tree stump removal.
Night work is scheduled Monday through Tuesday, July 23 and 24, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.
Green to Vallejo: Monday through Wednesday, July 16 through July 18, crews are also scheduled to complete permitted sidewalk tree stump removal.
Night work is scheduled Monday and Tuesday, July 23 and 24, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.
Vallejo to Broadway: Monday through Wednesday, July 16 through July 18, crews are scheduled to complete permitted sidewalk tree stump removal.
Night work is scheduled Monday and Tuesday, July 23 and July 24, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.
Broadway to Pacific: Monday through Friday, July 16 through July 20, and Monday through Friday, July 23 through July 27, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Monday through Wednesday, July 16 through July 18, crews are also scheduled to complete permitted sidewalk tree stump removal.
Night work is scheduled Monday through Wednesday, July 16 through July 18, and Monday and Tuesday, July 23 and July 24, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.
Pacific to Jackson: Monday through Friday, July 16 through July 20, and Monday through Friday, July 23 through July 27, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Monday through Wednesday, July 16 through July 18, crews are also scheduled to complete permitted sidewalk tree stump removal.
Night work is scheduled Monday, July 16, through Wednesday, July 18, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.
Jackson to Washington: Monday through Wednesday, July 16 through July 18, crews are scheduled to complete permitted sidewalk tree stump removal. Monday through Friday, July 16 through July 20, and Monday through Friday, July 23 through July 27, crews are scheduled to prepare the area for upcoming work.
Washington to Clay: Monday through Friday, July 16 through July 20, and Monday through Friday, July 23 through July 27, crews are scheduled to prepare the area for upcoming work.
Clay to Sacramento: Monday through Friday, July 16 through July 20, and Monday through Friday, July 23 through July 27, crews are scheduled to prepare the area for upcoming work.
Sacramento to California: Monday through Friday, July 16 through July 20, and Monday through Friday, July 23 through July 27, crews are scheduled to prepare the area for upcoming work.
California to Pine: Monday through Friday, July 16 through July 20, and Monday through Friday, July 23 through July 27, crews are scheduled to prepare the area for upcoming work.
Night work is scheduled Friday, July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.
Pine to Bush: Monday through Friday, July 16 through July 20, and Monday through Friday, July 23 through July 27, crews are scheduled to prepare the area for upcoming work.
Night work is scheduled Friday, July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.
Bush to Sutter: Monday through Friday, July 16 through July 20, and Monday through Friday, July 23 through July 27, crews are scheduled to work on sewer main installation and to prepare the area for upcoming work. Intensive noise and vibration is expected. Monday through Wednesday, July 16 through July 18, crews are also scheduled to complete permitted sidewalk tree stump removal.
Night work is scheduled Friday, July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.
Sutter to Post: Monday through Friday, July 16 through July 20, and Monday through Friday, July 23 through July 27, crews are scheduled to work on sewer main installation and to prepare the area for upcoming work. Intensive noise and vibration is expected. Monday through Wednesday, July 16 through July 18, crews are scheduled to complete permitted sidewalk tree stump removal. Monday, through Friday July 23 through July 27, crews are also scheduled to pothole for upcoming work.
Night work is scheduled Monday through Friday, July 16 through July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.
Post to Geary: Monday through Friday, July 16 through July 20, and Monday through Friday, July 23 through July 27,crews are scheduled to work on sewer main installation. Monday through Wednesday, July 16 through July 18, crews are also scheduled to complete permitted sidewalk tree stump removal.
Night work is scheduled Monday through Friday, July 16 through July 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.
Geary to O'Farrell: Monday through Friday, July 16 through July 20, and Monday through Friday, July 23 through July 27, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected Monday through Friday, July 16 through July 20, crews are also scheduled to complete permitted sidewalk tree stump removal and to pothole for upcoming work. Wednesday through Friday, July 25 through July 27, crews are also scheduled to install a joint-utility trench.
Night work is scheduled Monday through Friday, July 16 through July 20, and Monday through Friday, July 23 through July 27, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on updating the emergency firefighting water system. Disruptive noise is expected.
O’Farrell to Ellis: Monday through Friday, July 16 through July 20, and Monday through Friday, July 23 through July 27, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Monday through Wednesday, July 16 through July 18, crews are scheduled to complete permitted sidewalk tree stump removal. Monday through Friday, July 23 through July 27, crews are scheduled to install a joint-utility trench.
Ellis to Eddy: Monday through Wednesday, July 16 through July 18, crews are scheduled to complete permitted sidewalk tree stump removal. Monday through Friday, July 16 through July 20, and Monday through Friday, July 23 through July 27, crews are scheduled to install a joint-utility trench.
Eddy to Turk: Monday through Friday, July 16 through July 20, and Monday and Tuesday, July 23, and 24, crews are scheduled to install a joint-utility trench. Monday through Friday, July 16 through July 20, and Monday through Friday, July 23 through July 27, crews are also scheduled to complete permitted sidewalk tree stump removal.
Turk to Golden Gate: Monday through Friday, July 16 through July 20, and Monday through Friday, July 23 through July 27, crews are scheduled to update the emergency firefighting water system and to install a joint-utility trench. Monday through Friday, July 16 through July 20, and Monday through Friday, July 23 through July 27, crews are also scheduled to complete permitted sidewalk tree stump removal.
Night work is scheduled Monday through Friday, July 27 through July 23, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on updating the emergency firefighting water system. Disruptive noise is expected.
McAllister to Grove: Monday and Tuesday, July 16 and 17, crews are scheduled to prepare the area for upcoming sewer work. Tuesday through Friday, July 17 through July 20, crews are scheduled to work on water main installation. Wednesday through Friday, July 18 through July 20, and Monday through Friday, July 23 through July 27, crews are scheduled to work on sewer main installation and to work on the overhead contact system. Due to sewer work, intensive noise and vibration is expected.
Grove to Hayes: Monday and Tuesday, July 16 and 17, crews are scheduled to prepare the area for upcoming sewer work. Wednesday through Friday, July 18 through July 20, and Monday through Friday, July 23 through July 27, crews are scheduled to work on sewer main installation and to work on the overhead contact system. Due to sewer work, intensive noise and vibration is expected.
Hayes to Fell: Monday and Tuesday, July 16 and 17, crews are scheduled to prepare the area for upcoming sewer work. Wednesday, July 18, through Friday, July 20, and Monday, July 23, through Tuesday, July 24, crews are scheduled to work on the overhead contact system.
Fell to Market: Monday and Tuesday, July 16 and 17, crews are scheduled to prepare the area for upcoming sewer work. Wednesday, July 18, through Friday, July 20, and Monday, July 23, through Tuesday, July 24, crews are scheduled to work on the overhead contact system.
Market to Mission: Monday and Tuesday, July 16 and 17, crews are scheduled to prepare the area for upcoming sewer work. Wednesday through Friday, July 18 through July 20, and Monday and Tuesday, July 23 and 24, crews are scheduled to work on the overhead contact system.
Night work is scheduled Monday through Friday, July 16 through July 20, and Monday through Friday, July 23 through July 27, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.