L Taraval Improvement Forecast and Project Segment B Update – March 13 – 25, 2023

The below construction schedule has been amended to extend some weekday hours and add a few Saturdays: 

  • March 20 – March 31, 2023: Construction crews will work evenings until 6:30 p.m. on 15th, 17th, 18th, 20th and 21st avenues between Ulloa and Taraval streets and on 28th Avenue at Taraval Street
  • March 25 and April 1, 2023: Saturday work is scheduled between 8 a.m. and 4:30 p.m. on 15th, 17th, 18th, 20th and 21st avenues between Ulloa and Taraval streets and on 28th Avenue at Taraval Street
  • March 15 to 16 and March 20 to 23: Construction crews will work evenings until 6:30 p.m. on 29th, and 28th to 27th avenues.
  • March 18 and March 25: Saturday work is scheduled between 8 a.m. and 4:30 p.m. on 29th, and between 26th and 27th avenues.