This page has older content

Please see Related Projects on this page for current project information. See Travel & Transit Updates for current travel updates. We are keeping this page as a record of SFMTA service and outreach.

Van Ness Avenue Construction Forecast: October 2 - October 13, 2017

Share this:
Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit sfmta.com/vanness.

Work is planned over the next months to create two construction zones: one southbound on Van Ness Avenue from Sutter to McAllister streets, and another northbound from Jackson to Lombard streets. These work areas will be approximately five feet from the building line to approximately the center of the roadway.

To make space for these construction zones, blue curb parking for people with disabilities and loading zones are being temporarily relocated. (See map for locations.)

Project staff is reaching out directly to businesses and residents on blocks that are impacted by these changes. See the full schedule of expected activities below.

Those who travel in and through the area are advised to take alternate routes and plan for delays.

Monday, October 2, through Friday, October 6: Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission streets.

Monday, October 9, through Friday, October 13: Traffic control maintenance and construction site preparation will be conducted on Van Ness between Lombard and Mission streets.

Contact