Van Ness Avenue Construction Forecast: June 30 - July 12, 2019

Share this:
Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit
Walking

Tentative schedule:

In the next two weeks crews are scheduled to work on water main installation, sidewalk replacement, restoring the street base, paving, installing a joint-utility trench, installing light poles, street light conduits, and potholing for upcoming work.

The work listed below is scheduled for daytimes, 7:00 a.m. to 8:00 p.m. Planned night work is italicized. The night shift for construction is 8:00 p.m. to 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.

Sunday, June 30

  • Sacramento to California
  • California to Pine
  • Pine to Bush

Monday through Wednesday, July 1 through July 3

  • Chestnut to Lombard
  • Lombard to Greenwich Night work is also scheduled Monday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Greenwich to Filbert Night work is also scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Filbert to Union Night work is also scheduled Monday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Washington to Clay (Tuesday only)
  • Clay to Sacramento
  • Sacramento to California Night work is also scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m.
  • California to Pine
  • Pine to Bush Night work is also scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Bush to Sutter
  • Sutter to Post
  • Geary to O'Farrell
  • O'Farrell to Ellis (Monday and Tuesday only) Night work is also scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Ellis to Eddy (Monday and Tuesday only) Night work is also scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Eddy to Turk Night work is scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Turk to Golden Gate Night work is scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Golden Gate to McAllister Night work is also scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m.
  • McAllister to Grove (Monday only) Night work is also scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Grove to Hayes (Monday only) Night work is also scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Hayes to Fell (Monday only) Night work is also scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Fell to Market Night work is also scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Market to Mission Night work is scheduled Monday through Wednesday, between the hours of 8:00 p.m. and 7:00 a.m. *Intensive noise and vibration is expected.
  • Mission to Howard Night work is scheduled Monday through Wednesday, between the hours of 8:00 p.m. and 7:00 a.m. *Intensive noise and vibration is expected.
  • Mission and Franklin Night work is also scheduled Monday and Tuesday, between the hours of 8:00 p.m. and 7:00 a.m. *Disruptive noise is expected.

Monday through Friday, July 8 through July 12

*Northbound lanes from Lombard to Jackson will be shifted on the night of July 10 for the upcoming traffic and construction shift.

  • Chestnut to Lombard Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Lombard to Greenwich Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Greenwich to Filbert Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Filbert to Union Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Clay to Sacramento (Monday to Wednesday only)
  • Sacramento to California Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • California to Pine Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Pine to Bush Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • Bush to Sutter Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
  • O'Farrell to Ellis
  • Ellis to Eddy
  • Eddy to Turk
  • Turk to Golden Gate *Intensive noise is expected.
  • Golden Gate to McAllister *Intensive noise is expected.
  • Fell to Market
  • Market to Mission Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. *Intensive noise and vibration is expected.
  • Mission to Howard Night work is scheduled Sunday, between the hours of 8:00 p.m. and 7:00 a.m. *Intensive noise and vibration is expected.
  • Mission and Franklin Night work is also scheduled Monday, between the hours of 8:00 p.m. and 7:00 a.m.