The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit sfmta.com/vanness.
The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.
Tentative Schedule:
Monday, June 18, through Friday, June 22, and Monday, June 25, through Friday, June 29, crews are expected to prepare the median on Van Ness Avenue for upcoming work, from Lombard Avenue to Mission Street.
Lombard to Greenwich: Monday, June 25, through Friday, June 29, crews are scheduled to work on sewer installation. Intensive noise and vibration is expected.
Night work is scheduled Monday, June 18, through Friday, June 22, and Monday, June 25, through Friday, June 29, when crews are scheduled to work on sewer and water main installation. Disruptive noise is expected.
Union to Green: Monday, June 18, through Friday, June 22, crews are scheduled to work on water main installation. Disruptive noise is expected.
Broadway to Pacific: Monday, June 18, through Friday, June 22, and Monday, June 25, through Friday, June 29, crews are scheduled to work on sewer and water main installation. Due to sewer installation work, intensive noise and vibration is expected.
Pacific to Jackson: Monday, June 18, through Friday, June 22, and Monday, June 25, through Friday, June 29, crews are scheduled to work on sewer and water main installation. Due to sewer installation work, intensive noise and vibration is expected.
Washington to Clay: Night work is scheduled Thursday, June 21, through Friday, June 22, and Monday, June, 25, through Friday, June 29, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.
Clay to Sacramento: Night work is scheduled Thursday, June 21, through Friday, June 22, and Monday, June, 25, through Friday, June 29, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.
Sacramento to California: Night work is scheduled Thursday, June 21, through Friday, June 22, and Monday, June, 25, through Friday, June 29, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.
California to Pine: Night work is scheduled Thursday, June 21, through Friday, June 22, and Monday, June, 25, through Friday, June 29, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.
Pine to Bush: Night work is scheduled Thursday, June 21, through Friday, June 22, and Monday, June, 25, through Friday, June 29, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.
Bush to Sutter: Monday, June 18, through Friday, June 22, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.
Night work is scheduled Monday, June 18, through Friday, June 22, and Monday, June 25, through Friday, June 29, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.
Sutter to Post: Monday, June 18, through Friday, June 22, crews are scheduled to work on sewer main installation and to install a joint-utility trench. Due to sewer installation work, intensive noise and vibration is expected.
Night work is scheduled Monday, June 18, through Wednesday, June 20, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.
Post to Geary: Monday, June 18, through Friday, June 22, and Monday, June 25, through Friday, June 29, crews are scheduled to work on sewer and water main installation. Due to sewer installation work, intensive noise and vibration is expected.
Night work is scheduled Monday, June 25, through Friday, June 29, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation.
O’Farrell to Ellis: Monday, June 18, through Friday, June 22, and Monday, June 25, through Friday, June 29, crews are scheduled to work on sewer main installation and to install a joint-utility trench. Due to sewer installation work, intensive noise and vibration is expected. Monday, June 18, through Friday, June 22, crews are also scheduled to work on water main installation.
Night work is scheduled Monday, June 18, through Friday, June 22, and Monday, June 25, through Friday, June 29, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation.
Ellis to Eddy: Monday, June 18, through Friday, June 22, and Monday, June 25, through Friday, June 29, crews are scheduled to work on sewer main installation and to install a joint-utility trench. Due to sewer installation work, intensive noise and vibration is expected. Monday, June 18, through Friday, June 22, crews are also scheduled to work on water main installation.
Night work is scheduled Monday, June 25, through Friday, June 29, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on water main installation.
Eddy to Turk: Monday, June 18, through Friday, June 22, and Monday, June 25, through Friday, June 29, crews are scheduled to work on sewer main installation and to install a joint-utility trench. Due to sewer installation work, intensive noise and vibration is expected.
Turk to Golden Gate: Monday, June 18, through Friday, June 22, and Monday, June 25, through Friday, June 29, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.
Night work is scheduled Monday, June 18, through Friday, June 22, and Monday, June 25, through Friday, June 29, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on updating the emergency firefighting water system. Disruptive noise is expected.
Golden Gate to McAllister: Monday, June 18, through Friday, June 22, and Monday, June 25, through Friday, June 29, crews are schedule to work on roadway restoration.
Night work is scheduled Monday, June 18, through Friday, June 22, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on updating the emergency firefighting water system. Disruptive noise is expected.
Market to Mission: Night work is scheduled Friday, June 22, and Monday, June 25, through, Friday, June 29, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.