The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.
All night work is italicized below. The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.
Tentative schedule:
In the next two weeks crews are scheduled to work on sewer and water main installation, sidewalk replacement, installing a joint utility trench and street light conduits, and potholing for upcoming work.
Monday through Friday, February 25 through March 1
- Chestnut to Lombard. Night work is scheduled Monday and Tuesday between the hours of 8:00 p.m. and 7:00 a.m.
- Lombard to Greenwich. (Wednesday through Friday only) Night work is also scheduled Monday through Thursday between the hours of 8:00 p.m. and 7:00 a.m.
- Greenwich to Filbert. Night work is scheduled Monday through Thursday between the hours of 8:00 p.m. and 7:00 a.m.
- Filbert to Union. (Thursday only) Night work is also scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Union to Green. Night work is scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Green to Vallejo. Night work is scheduled Wednesday and Thursday between the hours of 8:00 p.m. and 7:00 a.m.
- Vallejo to Broadway. Night work is scheduled Wednesday and Thursday between the hours of 8:00 p.m. and 7:00 a.m.
- Clay to Sacramento. Night work is scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Sacramento to California. (Thursday and Friday only) *Intensive noise and vibration is expected. Night work is also scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- California to Pine. (Thursday and Friday only) *Intensive noise and vibration is expected.
- Bush to Sutter. Night work is scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Sutter to Post. Night work is also scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Post to Geary. Night work is also scheduled Tuesday and Wednesday, between the hours of 8:00 p.m. and 7:00 a.m.
- Geary to O'Farrell. Night work is also scheduled Tuesday and Wednesday, between the hours of 8:00 p.m. and 7:00 a.m.
- O'Farrell to Ellis. Night work is scheduled Tuesday and Wednesday, between the hours of 8:00 p.m. and 7:00 a.m.
- Ellis to Eddy. Night work is scheduled Tuesday and Wednesday, between the hours of 8:00 p.m. and 7:00 a.m.
- Eddy to Turk. Night work is scheduled on Tuesday and Wednesday, between the hours of 8:00 p.m. and 7:00 a.m.
- Turk to Golden Gate. Night work is also scheduled Monday through Wednesday, between the hours of 8:00 p.m. and 7:00 a.m.
- Golden Gate to McAllister. Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- McAllister to Grove. Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Grove to Hayes. Night work is also scheduled on Monday, February 25, between the hours of 8:00 p.m. and 7:00 a.m.
- Hayes to Fell. Night work is also scheduled on Monday, February 25, between the hours of 8:00 p.m. and 7:00 a.m.
- Fell to Market. (Thursday and Friday only) Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. *Intensive noise and vibration is expected on Monday and Tuesday. Disruptive noise is expected Wednesday through Friday.
- Market to Mission.
Monday through Friday, March 4 through March 8
- Lombard to Greenwich.
- Greenwhich to Filbert.
- Filbert to Union. Night work is scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Union to Green. Night work is scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Vallejo to Broadway. (Friday only)
- Broadway to Pacific. (Friday only)
- Pacific to Jackson. (Friday only)
- Washington to Clay. Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Clay to Sacramento. Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Sacramento to California. *Intensive noise and vibration is expected. Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- California to Pine. *Intensive noise and vibration is expected. Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- O'Farrell to Ellis. (Wednesday through Friday only)
- Ellis to Eddy.
- Golden Gate to McAllister. Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- McAllister to Grove. Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Grove to Hayes.
- Fell to Market. *Intensive noise and vibration is expected.
*We are working on improving the format of our weekly construction forecasts. Please share your feedback with staff at VanNessBRT@SFMTA.com