Central Subway Construction Update 4/18/14
Construction Update April 19 - 28, 2014 During the next 10 days, Central Subway work will continue at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates about...
Construction Update April 19 - 28, 2014 During the next 10 days, Central Subway work will continue at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates about...
Central Subway Project Advancements January 17 - January 26, 2015 This section contains brief updates about recent construction activities and a look-ahead for what to expect in Southern SoMa...
Project Advancements August 16 - August 25, 2014 During the next 10 days, Central Subway work continues at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates...
Note: Updated information as of 6:02 pm, 5/16/14. At 4th and Bryant I-80 off-ramp, three lanes may be closed on weeknights from 12 a.m. to 5 a.m. and one lane may be closed during the daytime from 10...
Construction Update October 19-28, 2013 During the next 10 days, tunneling and tunneling preparatory work will continue in SoMa, Union Square and North Beach. Work to prepare for station construction...
Central Subway Project Advancements May 9 - May 18, 2015 This section contains brief updates about recent construction activities and a look-ahead for what to expect in Southern SoMa, Northern SoMa...
Construction Update June 21 - June 30, 2014 During the next 10 days, Central Subway work will continue at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates...
Central Subway Project Advancements February 28 - March 9, 2015 This section contains brief updates about recent construction activities and a look-ahead for what to expect in Southern SoMa, Northern...
Construction Update July 04 - July 14, 2014 During the next 10 days, Central Subway work will continue at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates...
Construction Update September 21-30, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. In North Beach, demolition of the Pagoda Palace will...
A message from SFMTA Director of Transportation Edward D. Reiskin 2015 was a very exciting year for the Central Subway project as we made tremendous advancement in construction; in fact the project is...
Central Subway Project Advancements January 31 - February 9, 2015 This section contains brief updates about recent construction activities and a look-ahead for what to expect in Southern SoMa...
Central Subway Project Advancements February 21 - March 2, 2015 This section contains brief updates about recent construction activities and a look-ahead for what to expect in Southern SoMa, Northern...
Construction Update November 16-25, 2013 During the next 10 days, tunneling and tunneling preparatory work will continue in SoMa, Union Square and North Beach. Work to prepare for station construction...
Central Subway Project Advancements April 4 - April 13, 2015 This section contains brief updates about recent construction activities and a look-ahead for what to expect in Southern SoMa, Northern...
Central Subway Project Advancements May 2 - May 11, 2015 This section contains brief updates about recent construction activities and a look-ahead for what to expect in Southern SoMa, Northern SoMa...
January 11-20, 2014 During the next 10 days, Central Subway work will continue at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates about what is happening in...
Project Advancements September 13 - September 22, 2014 During the next 10 days, Central Subway work continues at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief...
Construction Update October 25-November 4, 2013 During the next 10 days, tunneling and tunneling preparatory work will continue in SoMa, Union Square and North Beach. Work to prepare for station...
Project Advancements September 6 - September 15, 2014 During the next 10 days, Central Subway work continues at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief...
Construction Update December 7-16, 2013 We completed an important construction milestone last week as our tunneling contractor and TBM Mom Chung successfully and safely tunneled under Market Street...
Project Advancements January 3, 2015 - January 12, 2015 During the next 10 days, Central Subway construction work continues at sites in SoMa, Union Square, Chinatown and North Beach. This section...
The SFMTA is proposing a parking protected bikeway on Fell Street between Baker Street and Shrader Street to provide relief to crowding and support social distancing on the Panhandle Path. This...
Project Advancements October 18 - October 27, 2014 During the next 10 days, Central Subway work continues at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates...