The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.
The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.
Tentative schedule:
In the next two weeks crews are scheduled to work on sewer and water main installation, sidewalk replacement, installing a joint utility trench, street light conduits and potholing for upcoming work.
Monday through Friday, November 26, through November 30
- Bay to Francisco (Monday through Wednesday only)
- Chestnut to Lombard
- Lombard to Greenwich
- Filbert to Union
- Union to Green
- Green to Vallejo
- Vallejo to Broadway
- Broadway to Pacific
- Pacific to Jackson
- Jackson to Washington
- Washington to Clay
- California to Pine (Thursday and Friday only) *Intensive noise and vibration is expected.
- Bush to Sutter (Monday through Wednesday only) *Intensive noise and vibration is expected.
- Geary to O'Farrell Night work is also scheduled Friday, November 30, between the hours of 8:00 p.m. and 7:00 a.m.
- O'Farrell to Ellis Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Ellis to Eddy Night work is scheduled Monday through Thursday, between the hours of 8:00 p.m. and 7:00 a.m.
- McAllister to Grove
- Grove to Hayes
- Hayes to Fell *Intensive noise and vibration is expected.
- Fell to Market *Intensive noise and vibration is expected. Night work is also scheduled Thursday and Friday, between the hours of 8:00 p.m. and 7:00 a.m. Intensive noise and vibration is expected.
Saturday, December 1
- Chestnut to Lombard
- Lombard to Greenwich
Monday through Friday, December 3 through December 7
- Chestnut to Lombard Night work is scheduled Monday through Thursday, between the hours of 8:00 p.m. and 7:00 a.m. Disruptive noise is expected.
- Lombard to Greenwich Night work is scheduled Monday through Thursday, between the hours of 8:00 p.m. and 7:00 a.m. Disruptive noise is expected.
- Greenwich to Filbert
- Filbert to Union
- Union to Green
- Washington to Clay *Intensive noise and vibration is expected. Night work is also scheduled Wednesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. Intensive noise and vibration is expected.
- Clay to Sacramento *Intensive noise and vibration is expected. Night work is also scheduled Wednesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. Intensive noise and vibration is expected.
- California to Pine *Intensive noise and vibration is expected. Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. Intensive noise and vibration is expected.
- Pine to Bush (Thursday and Friday only) Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. Intensive noise and vibration is expected.
- Sutter to Post
- Post to Geary Night work is also scheduled Thursday and Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Geary to O'Farrell *Access to Myrtle Street from the west side of Van Ness will be limited. Night work is also scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- O'Farrell to Ellis Night work is scheduled Monday through Wednesday, between the hours of 8:00 p.m. and 7:00 a.m.
- Ellis to Eddy
- Eddy to Turk
- McAllister to Grove (Tuesday through Friday only)
- Grove to Hayes (Tuesday through Friday only)
- Fell to Market (Monday through Wednesday only) Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. Intensive noise and vibration is expected.