The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit sfmta.com/vanness.
The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.
Tentative Schedule:
Lombard to Greenwich: Tuesday through Thursday, July 24 through July 26, crews are scheduled to work on permitted sidewalk tree stump removal. Monday through Friday, July 30 through August 3, crews are scheduled to work on sewer main installation.
Night work is scheduled Monday through Friday, July 23 through July 27, and Monday through Friday, July 30 through August 3, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Disruptive noise is expected. Also on Monday through Friday, July 23 through July 27, between the hours of 8:00 p.m. and 7:00 a.m., crews are scheduled to work on water main installation. Disruptive noise is expected.
Greenwich to Filbert: Tuesday through Thursday, July 24 through July 26, crews are scheduled to work on permitted sidewalk tree stump removal.
Filbert to Union: Tuesday through Thursday, July 24 through July 26, crews are scheduled to work on permitted sidewalk tree stump removal. Monday through Friday, July 30 through August 3, crews are scheduled to pothole for upcoming work.
Union to Green: Tuesday through Thursday, July 24 through July 26, crews are scheduled to work on permitted sidewalk tree stump removal.
Green to Vallejo: Tuesday through Thursday, July 24 through July 26, crews are scheduled to work on permitted sidewalk tree stump removal. Wednesday through Friday, July 25 through July 27, crews are scheduled to pothole for upcoming work.
Vallejo to Broadway: Monday, July 23, and Tuesday, July 24 crews are scheduled to pothole for upcoming work. Tuesday through Thursday, July 24 through July 26, crews are scheduled to work on permitted sidewalk tree stump removal.
Broadway to Pacific: Monday through Friday, July 23 through July 27, crews are scheduled to work on sewer main installation and to pothole for upcoming work. Tuesday through Thursday, July 24 through July 26, crews are also scheduled to work on permitted sidewalk tree stump removal.
Pacific to Jackson: Monday through Friday, July 23 through July 27, crews are scheduled to work on sewer and water main installation, and to pothole for upcoming work. Tuesday through Thursday, July 24 through July 26, crews are also scheduled to work on permitted sidewalk tree stump removal.
Jackson to Washington: Monday, July 23, and Tuesday, July 24 crews are scheduled to work on water main installation and to pothole for upcoming work. Tuesday through Thursday, July 24 through July 26, crews are scheduled to work on permitted sidewalk tree stump removal.
Clay: Monday, July 23, and Tuesday, July 24, crews are scheduled to prepare the area for upcoming sewer work.
Sutter to Post: Monday through Friday, July 23 through July 27, and Monday through Friday, July 30 through August 3, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected. Tuesday through Thursday, July 24 through July 26, crews are scheduled to work on permitted sidewalk tree stump removal.
Night work is scheduled Monday through Friday, July 23 through July 27, and Monday through Friday, July 30 through August 3, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work. Night work is also scheduled Thursday through Friday, July 26 through July 27, and Monday through Friday, July 30 through August 3, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation. Disruptive noise is expected.
Post to Geary: Monday through Friday, July 23 through July 27, crews are scheduled to work on sewer main installation. Disruptive noise is expected. Tuesday through Thursday, July 24 through July 26, crews are scheduled to work on permitted sidewalk tree stump removal.
Night work is scheduled Monday through Friday, July 23 through July 27, and Monday through Friday, July 30 through August 3, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on sewer main installation and to pothole for upcoming work. Disruptive noise is expected.
Geary to O'Farrell: Monday through Friday, July 23 through July 27, crews are scheduled to work on sewer main installation. Disruptive noise is expected. Tuesday through Thursday, July 24 through July 26, crews are also scheduled to work on permitted sidewalk tree stump removal and water main installation. Wednesday through Friday, August 1 through August 3, crews are scheduled to install a joint-utility trench.
Night work is scheduled Monday through Friday, July 23 through July 27, and Monday through Friday, July 30 through August 3, between the hours of 8:00 p.m. and 7:00 a.m., when crews are expected to work on updating the emergency firefighting water system and to pothole to confirm underground utilities for upcoming sewer work. Also on Monday through Friday, July 23 through July 27, between the hours of 8:00 p.m. and 7:00 a.m., crews are scheduled to work on sewer main installation. Disruptive noise is expected.
O’Farrell to Ellis: Monday through Friday, July 23 through July 27, and Monday through Friday, July 31 through August 3, crews are scheduled to install a joint-utility trench. Monday through Thursday, July 23 through July 26, crews are also scheduled to work on water main installation and to complete permitted sidewalk tree stump removal.
Night work is scheduled Monday through Friday, July 23 through July 27, and Monday through Friday, July 30 through August 3, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work and work on updating the emergency firefighting system.
Ellis to Eddy: Monday through Friday, July 23 through July 27, and Monday through Tuesday, July 30 through 31, crews are scheduled to install a joint-utility trench. Monday through Thursday, July 23 through July 26, crews are also scheduled to perform water work and permitted sidewalk tree stump removal.
Night work is scheduled Monday through Friday, July 23 through July 27, and Monday through Friday, July 30 through August 3, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.
Eddy to Turk: Tuesday through Thursday, July 24 through July 26, crews are scheduled to work on permitted sidewalk tree stump removal. Monday through Friday, July 23 through July 27, and Monday through Friday, July 30 through August 3, crews are scheduled to install a joint-utility trench.
Night work is scheduled Monday through Friday, July 23 through July 27, and Monday through Friday, July 30 through August 3, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work.
Turk to Golden Gate: Monday through Friday, July 23 through July 27, and Monday through Friday, July 30 through August 3, crews are scheduled to update the emergency firefighting water system. Tuesday through Thursday, July 24 through July 26, crews are also scheduled to work on permitted sidewalk tree stump removal. Tuesday through Friday, July 31 through August 3, crews are scheduled to install a joint-utility trench.
Night work is scheduled Monday through Friday, July 23 through July 27, and Monday through Friday, July 30 through August 3, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work and to work on updating the emergency firefighting system.
McAllister to Grove: Monday through Friday, July 23 through July 27, crews are scheduled to prepare the area for upcoming sewer work. Monday through Friday, July 30 through August 3, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.
Night work is scheduled Monday through Friday, July 23 through July 27, and Monday through Friday, July 30 through August 3, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work and to work on the overhead contact system. Also on Wednesday through Friday, July 25 through July 27, between the hours of 8:00 p.m. and 7:00 a.m., crews are scheduled to perform water work.
Grove to Hayes: Monday through Friday, July 23 through July 27, crews are scheduled to prepare the area for upcoming sewer work. Monday through Friday, July 30 through August 3, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.
Night work is scheduled Monday through Friday, July 23 through July 27, and Monday through Friday, July 30 through August 3, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on the overhead contact system.
Hayes to Fell: Monday through Friday, July 23 through July 27, and Monday through Friday, July 30 through August 3, crews are scheduled to work on sewer main installation. Intensive noise and vibration is expected.
Night work is scheduled Monday through Friday, July 23 through July 27, and Monday through Friday, July 30 through August 3, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on the overhead contact system.
Fell to Market: Night work is scheduled Thursday through Friday, July 26 through July 27, and Monday through Friday, July 30 through August 3, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on the overhead contact system.
Market to Mission: Night work is scheduled Monday through Friday, July 23 through July 27, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to pothole to confirm underground utilities for upcoming sewer work. Night work is also scheduled Thursday through Friday, July 26 through July 27, and Monday through Friday, July 30 through August 3, between the hours of 8:00 p.m. and 7:00 a.m., when crews are scheduled to work on the overhead contact system.