This page has older content

Please see Related Projects on this page for current project information. We are keeping this page as a record of SFMTA outreach.

Project Update - July 2020

Share this:
Service Affected
Bicycle
Parking
Driving

Construction Progress Update

The southbound direction of The Embarcadero between Mission to Howard streets was repaved and road markings were installed late-June. Five general parking meters are planned for installation on this block in August.

Southbound The Embarcadero between Mission and Howard streets after road was repaved and striping restored

What's Coming Next

Starting the week of July 27 general metered parking will be bagged for removal on the waterside of The Embarcadero between Harrison and Mission streets in preparation for construction of the Rincon Restaurant Zone and Ferry Terminal Quick-Build Projects.

Rincon Restaurant Zone Quick Build

The installation of road markings for the northbound protected bikeway, plastic posts, and extended passenger loading zone is expected to begin early August. Meters for motorcycle parking are expected to be installed late August/September.

Ferry Terminal Quick Build

The installation of road markings for the protected bikeway, plastic posts, and turn boxes is expected to begin early August. Concrete islands and railings to protect the two-way bikeway and bike signals at Howard Street are planned for installation in September.

NOTE: The Folsom-Mission protected bikeway will be northbound only until concrete islands are installed.

Pier 35 Quick Build

Construction of the Pier 35 segment is planned to begin in September.

Construction Impacts

During construction, crews will be repaving roadways, adding new paint to the road and curbs, removing and installing metered parking, and installing pedestrian/bicycle waiting areas and protected bikeways.

We ask for your patience and consideration as we work to bring these vital safety improvements to The Embarcadero corridor. General work hours will be from 8 a.m. to 5 p.m.

During construction, please look out for field staff and temporary signage and exercise care when using the street.

For more information, please visit The Embarcadero Quick Build project website at (SFMTA.com/EmbarcaderoQB) or email the project team at Embarcadero@SFMTA.com.

Contact