Lake Merced Boulevard Quick-Build Project Early 2025 Update

Share this:

Bicyclist on completed bikeway protected by transit boarding island

Construction of the Lake Merced Boulevard Quick-Build Project continued last month with the installation of new transit boarding islands to support Muni and Samtrans bus service. A total of six boarding islands will be built this year, starting with the first two at northbound Lake Merced Hills and northbound Brotherhood Way. The island at Lake Merced Hills is now complete, and Public Works crews are finishing up the island at Brotherhood Way.

Bus stops may be temporarily relocated while work sites are in active construction. Please look for posted notices and signage indicating the nearest stop. Thank you for your patience as we work to improve the street!

For more information about the project overall, please visit: SFMTA.com/LakeMercedQB