L Taraval Improvement Project – Segment B
Project Update September 12 - 24, 2022
Work continues on water and sewer lines, as well as on the overhead contact system (OCS). OCS work performed at night includes potholing, foundation work and installation of new poles. Construction teams will be excavating and jackhammering pavement, which may cause vibrations. Materials are also being staged nearby. Dust control and housekeeping measures are in place at active construction and staging locations.
General construction hours are Monday to Friday between 8:00 a.m. to 4:00 p.m. Night work below is italicized and takes place from 10 p.m. to 5 a.m. Construction schedules are subject to change. No parking signs will be posted in construction and staging areas, and intersections may be closed to through traffic on Taraval Street.
Multiple agencies in the area are performing infrastructure work. This includes Public Works on 19th Avenue, Public Utilities Commission at Vicente and Wawona streets and PG&E along Taraval Street.
Construction work is scheduled to be performed between September 12 - 24, 2022
Taraval Street
15th Avenue intersection: sewer work
17th to 19th avenues: water work, excavate and shoring
25th Avenue: water work
26th to 28th avenues: sewer work, excavate and shore connection
32nd Avenue: sewer work
30th to 36th avenues: OCS foundation and conduit work
36th Avenue to Sunset Blvd: waterline work
Ulloa Street from 15th to Forest Side avenues
Funston Street: Water work, install and test water system
Temporary staging locations
16th Avenue west side from Taraval to Ulloa streets
18th Avenue west side from Taraval to Ulloa streets
28th Avenue east side from Taraval to Ulloa streets
29th Avenue west side from Taraval to Santiago streets
36th Avenue west side from Taraval to Santiago streets