This page has older content

Please see Related Projects on this page for current project information. We are keeping this page as a record of SFMTA outreach.

L Taraval Improvement Forecast and Project Segment B Update – March 13 – 25, 2023

Share this:

The below construction schedule has been amended to extend some weekday hours and add a few Saturdays: 

  • March 20 – March 31, 2023: Construction crews will work evenings until 6:30 p.m. on 15th, 17th, 18th, 20th and 21st avenues between Ulloa and Taraval streets and on 28th Avenue at Taraval Street
  • March 25 and April 1, 2023: Saturday work is scheduled between 8 a.m. and 4:30 p.m. on 15th, 17th, 18th, 20th and 21st avenues between Ulloa and Taraval streets and on 28th Avenue at Taraval Street
  • March 15 to 16 and March 20 to 23: Construction crews will work evenings until 6:30 p.m. on 29th, and 28th to 27th avenues.
  • March 18 and March 25: Saturday work is scheduled between 8 a.m. and 4:30 p.m. on 29th, and between 26th and 27th avenues.

 

 

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit
Walking
Route(s) Affected

L Taraval Improvement Forecast and Project Segment B Update – March 13 – 25, 2023

In the coming weeks, work continues on water and sewer lines, as well as on the overhead contact system (OCS) that powers the trains. OCS work is now focused on foundation work to prepare for the installation of new poles. Construction teams will be excavating and jackhammering pavement, which may cause vibrations. Materials are also being temporarily staged nearby. Dust control and housekeeping measures are in place at active construction and staging locations. Extreme weather conditions may impact the construction schedule. 

The inbound bus stop at Taraval and 15th has been relocated across the intersection until fall 2024.

General construction hours are Monday to Friday between 8:00 a.m. and 4:00 p.m. Construction schedules are subject to change. “No Parking” signs will be posted in construction and staging areas, and intersections may be closed to through traffic on Taraval Street.

Multiple agencies are performing infrastructure work in the area. This includes work by Public Works on 19th Avenue, Public Utilities Commission at Vicente and Wawona streets and PG&E along Taraval Street.

L Taraval Improvement Project – Segment B

Construction work is scheduled to be performed - March 13 – 25, 2023

Taraval Street

16th to 18th avenues: OCS foundation and pole work

16th Avenue: water line work

17th, 18th, 19th avenues: intersection water line work, construct manholes

21st to 22nd avenues: demolish and grade curb ramp

22nd to 23rd avenues: OCS foundation and pole work

24th Avenue: waterline work, construct VCP culvert

25th to 29th avenues: water line work, excavating and shoring, backfill

28th to 29th avenues: OCS foundation and pole work

29th to 33rd avenues: water line work, excavating and shoring service laterals

29th to 30th avenues: OCS foundation and pole work

34th and 35th avenues: demolish and grade curb ramp

31st to 33rd avenues: water line work, excavating and shoring

34th to 35th avenues: construct sidewalk and curb ramp

33rd to 34th avenues: OCS foundation and pole work

Ulloa Street

14th to15th avenues: waterline work, excavating and shoring

14th to Funston avenues: waterline work, chlorinate and connect segments

Temporary staging locations

16th Avenue west side from Taraval to Ulloa streets

17th Avenue west side from Taraval to Ulloa streets

17th Avenue west side from Taraval to Santiago streets

22nd Avenue west side from Taraval to Santiago streets

28th Avenue east side from Taraval to Ulloa streets

Please sign up for email and SMS project updates on the project page.