This page has older content

Please see Related Projects on this page for current project information. We are keeping this page as a record of SFMTA outreach.

L Taraval Improvement Forecast and Project Segment B Update – February 9 - 25, 2023

Share this:
Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit
Walking
Website
Weekend Traffic and Transit Advisory
Route(s) Affected

L Taraval Improvement Forecast and Project Segment B Update –  February 9 - 25, 2023

In the coming weeks, work continues on water and sewer lines, as well as on the overhead contact system (OCS) that powers the trains. OCS work is now focused on foundation work to prepare for the installation of new poles. Construction teams will be excavating and jackhammering pavement, which may cause vibrations. Materials are also being temporarily staged nearby. Dust control and housekeeping measures are in place at active construction and staging locations.

The inbound bus stop at Taraval and 15th has been relocated across the intersection until fall 2024.

In observance of President’s Day, all construction will be suspended Monday, February 20, 2023.

General construction hours are Monday to Friday between 8:00 a.m. and 4:00 p.m. Construction schedules are subject to change. “No Parking” signs will be posted in construction and staging areas, and intersections may be closed to through traffic on Taraval Street.

Multiple agencies are performing infrastructure work in the area. This includes work by Public Works on 19th Avenue, Public Utilities Commission at Vicente and Wawona streets and PG&E along Taraval Street.

L Taraval Improvement Project – Segment B

Construction work is scheduled to be performed - February 9 – 25, 2023

Taraval Street

15th to 19th avenues: waterline work, excavate sewer laterals,water service change over*

22nd to 25th avenues: construct VCP crossing and sand trap, patch sewer manholes

24th avenue: install traffic signal conduit and pole

28th to 30th avenues: OCS pole work

31st to 33rd avenues: waterline work, excavate and shoring

32nd and 34th avenues: construct sidewalk and curb ramp

33rd Avenue: waterline work

33rd to 34th avenues: OCS pole work

Sunset Boulevard to 36th Avenue: waterline work

Ulloa Street

14th Avenue to Funston Street: water line work, excavation and shoring, water service change over*

Ulloa street and 14th Avenue: OCS pole work

Temporary staging locations

14th Avenue west side from Ulloa to Vicente streets

16th Avenue west side from Taraval to Ulloa streets

22nd Avenue west side from Taraval to Santiago streets

24th Avenue east side from Taraval to Santiago streets

26th Avenue east side from Tarava to Santiago streets

27th Avenue west side from Taraval to Ulloa streets

29th Avenue west side from Taraval to Santiago streets

33rd Avenue east side from Taraval to Santiago streets

*Water service to some properties may be briefly shut off while SFPUC connects to the new water main. SFPUC will notify properties in advance of any service interruption.