No work is planned on Monday, September 4 as crews observe the Labor Day holiday
Pulling rails to Taraval between 22nd and 25th avenues on Thursday, August 31 more info about track Replacement on the L Taraval line.
Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit
Walking
Neighborhoods Affected
Route(s) Affected
At approximately 2:00 pm, on August 29, during the street base demolition in preparation for the foundation pour between 29th and 30th avenues, the contractor accidentally damaged a shallow gas line located 6" below grade. PG&E responded promptly, starting repairs by 2:25 pm and completing them by 5:30 pm. The Fire Department was also on site and secured the area.
The construction crew also reported a second gas line, 9.5" below grade, as near 1920 Taraval. PGE inspected the line and determined the line to be inactive abandoned line. The line was cut and safely removed and capped with no incident.
Please know that safety is our top priority and we made sure that the appropriate team was in place to address the issue.