This page has older content

Please see Related Projects on this page for current project information. We are keeping this page as a record of SFMTA outreach.

Geary Rapid Project Construction Forecast: November 30, 2019 - December 13, 2019

Share this:
Service Affected
Accessibility
Parking
Driving
Transit
Walking

As part of the Geary Rapid Project, work to replace aging water and sewer lines on Geary Boulevard, in coordination with San Francisco Public Utilities Commission, continues. East of Van Ness Avenue, contractors will be observing the holiday construction moratorium beginning November 27, 2019 until January 2020.

The following two-week construction forecast is subject to change due to weather delays or unexpected field conditions.

Masonic Avenue – Gough Street
Mondays through Fridays between 8:00 a.m. and 7:00 p.m.:

  • Concrete roadway base work is planned for the weeks of December 2 and December 9 on Geary Boulevard between Lyon and Fillmore streets.
  • Sewer main replacement is planned for the weeks of December 2 and December 9 between Buchanan and Cleary streets.

Some parking will be temporarily restricted in construction zones and traffic lanes will be modified during active work.

Holiday Moratorium to Begin for Work East of Van Ness

In accordance with City policy to support small businesses during the busy holiday season, the holiday moratorium will be observed for the Geary East contract beginning on Thanksgiving, Thursday, November 28. Crews will demobilize beginning on Wednesday, November 27, and equipment will be removed from the area until after January 1, 2020. Work to replace water mains is expected to begin again on Geary Street between Polk and Hyde Streets in early January.

West of Van Ness Avenue, contractors plan to continue utility work through December.

Questions or concerns? Contact us at GearyRapid@SFMTA.com or 415.646.2300.


Geary Rapid Project Schedule

Geary Rapid Project Construction Timeline  Geary Rapid Project Construction timeline that ranges from 2018 until 2021. There are red, blue and yellow lines extending from 2018 until 2021. The red line represents transit and safety treatments that include bus-only lanes, pedestrian safety improvements, bus stop changes and roadway striping changes. The blue line represents utility upgrades that include watermain replacement on Geary (Masonic to Market), sewer main replacement (primarily Masonic to Van Ness) and fiber-optic cable conduits (Stanyan to Gough). The yellow lines represent major transit and safety improvements that include bus bulbs, pedestrian bulbs, upgraded traffic signals and roadway repaving (Masonic to Van Ness).  The timeline is broken into two sections.   The first section is Stanyan to Van Ness. There is a red line in the 2018 portion of the timeline representing the transit and safety treatments, a blue line that extends from mid 2018 until mid 2020 representing utility upgrades and a yellow line extending from the end of 2019 until mid 2021 representing major transit and safety improvements. In the beginning of the 2020 portion of the timeline is a bridge symbol that represents the demolition of the Steiner Street pedestrian bridge over an entire weekend.   The second section is Van Ness to Market. There is a red line representing transit and safety treatments that extends within 2018, a blue line representing utility upgrades that extends from the beginning of 2019 until near the end of 2020, and a yellow line representing major transit and safety improvements that extends from mid 2019 until mid 2021. Work is currently underway on two of the four total construction contracts that comprise the Geary Rapid Project. While construction remains on schedule, some of the contracts were advertised later than originally expected. As a result, the project overall is now expected to be substantially completed in mid-2021.


The following 38/38R bus stops are planned to be temporarily relocated. These changes are part of work that is unrelated to the Geary Rapid Project.

  • Mondays - Sundays, November 1 - December 31, all day:
    The inbound 38/38R Geary bus stop on O'Farrell Street at Van Ness Avenue will be temporarily relocated west towards Franklin Street while work related to the Van Ness Improvement Project is performed.
  • Mondays - Sunday, November 8 - November 27, all day:
    The inbound 38/38R Geary bus stop on O'Farrell at Powell Street will be temporarily shifted slightly west during utility excavation work.
  • Mondays - Fridays, November 14 - December 13, 8:00 a.m. to 4:00 p.m.
    The inbound 38/38R Geary/38-AX "A" Express bus stop on Geary Boulevard and 39th Avenue will be temporarily relocated west before the existing stop to the far side of Geary Boulevard and 40th Avenue during construction.

To view a map of temporary bus stop relocations citywide, please visit: SFMTA.com/TempStopMap