Photo: 38 Geary bus at Geary and Webster
As part of the Geary Rapid Project, work to replace aging water lines, in coordination with San Francisco Public Utilities Commission, continues. Surface transportation improvements, including upgraded traffic signals and streetlights, sidewalk extensions at bus stops and intersection corners, improved median refuges and roadway repaving, are also underway and are being managed by San Francisco Public Works.
The following two-week construction forecast is subject to change due to weather delays or unexpected field conditions. No work is planned on Monday, May 31 as crews are observing the Memorial Day holiday.
Steiner Street – Van Ness Avenue
Mondays through Fridays between 8:00 a.m. and 7:00 p.m.:
-
Sidewalk and median work is planned for the weeks of May 24 and June 1 on Geary Boulevard at the intersections of Webster Street and Buchanan Street.
-
Construction of the expanded patio at Hamilton Recreation Center on Steiner Street is planned for the weeks of May 24 and June 1. Work is scheduled to begin at 7:00 a.m. at this location.
Van Ness Avenue – Market Street
Mondays through Fridays between 7:00 a.m. and 4:00 p.m.:
-
Water service connection work is planned for the weeks of May 24 and June 1 on Geary Street between Stockton and Kearny streets.
-
Water service to some properties may be briefly shut off while SFPUC connects to the new water main on Geary. SFPUC will notify properties in advance of any service interruption. To minimize disruption, work is sometimes conducted at night.
-
Roadway and sidewalk work is planned for the weeks of May 24 and June 1 at the intersections of Geary and Mason streets and O’Farrell and Grant streets.
-
During active roadway work, the inbound 38/38R Geary at Grant will be relocated east towards Market Street. Look for “Board Here” signs.
Some parking will be temporarily restricted in construction zones and traffic lanes will be modified during active work. There may be brief vibrations during sidewalk and roadway excavation.
Questions or concerns? Contact us at GearyRapid@SFMTA.com or 415.646.2300.
Shop Local
You can help San Francisco's vibrant commercial life rebound from COVID-19 by visiting local businesses in the Fillmore, Japantown, the Tenderloin and Union Square. As San Francisco begins to reopen from the latest citywide shutdown order, please check with individual businesses to confirm that they are open.
For customers:
Shop & Dine in the 49. Find information about how to support local restaurants and businesses throughout San Francisco.
For businesses:
Grant Program: Grants for storefront businesses that have received little to no federal or city funding, businesses forced to close for 6+ months, long-established businesses and businesses in high-need neighborhoods. Amounts range from $5,000-$25,000.
San Francisco Community Investment Loan Program: Low to zero-interest loans up to $100,000.
NEW: Do you have a Place of Entertainment permit? Apply for a live music and entertainment grant.
California Grants:
Small businesses and nonprofits may be eligible for the California Small Business COVID-19 Relief Grant Program. Learn more at CAReliefGrant.com.
There are no planned temporary 38/38R bus stop relocations this week that are part of work that is unrelated to the Geary Rapid Project.
View a map of temporary bus stop relocations citywide.
For the most up-to-date Muni service information, parking enforcement and other updates visit SFMTA.com/COVID19.