Dr. Carlton B. Goodlett Place Quick-Build Project: Construction starting 10/2/24

Share this:

The Dr. Carlton B. Goodlett Place Quick-Build Project was approved by the San Francisco Municipal Transportation Agency Board at the October 1, 2024 meeting.

Link to meeting page with agenda, staff report: October 1, 2024 SFMTA Board Meeting

Link to illustration of the approved project design: Project Design

Construction is starting today and is expected to wrap up by November 1, 2024. Below is the working construction schedule, which is subject to change:

  • Roadway resurfacing: 10/2-10/16, starting with base repair on the southbound side of the corridor
  • Roadway striping and sign installation: 10/17-11/1
  • Construction of intersection islands at the McAllister and Grove intersections: 10/18-10/25

Questions? Please reach out to Julia.malmo@sfmta.com 