Dr. Carlton B. Goodlett Place Quick-Build Project: 10/9/24 Construction update

Share this:

Construction of the Dr. Carlton B. Goodlett Place Quick-Build Project is underway! Construction is still expected to wrap up by November 1, 2024. Below is the working implementation schedule, which is subject to change and weather dependent:

  • Roadway resurfacing: estimated 10/2-10/10, work currently underway on the northbound side of the corridor
  • Roadway striping and sign installation: estimated 10/11-10/18
  • Construction of intersection islands at the McAllister and Grove intersections: estimated 10/18-10/25

Questions? Please reach out to Julia.malmo@sfmta.com 