Dr. Carlton B. Goodlett Place Quick-Build Project: 10/23/24 Construction update

Share this:

Construction of the Dr. Carlton B. Goodlett Place Quick-Build construction is progressing, and we anticipate substantial completion by November 1, 2024. Below is the working construction schedule, which is subject to change and weather dependent:

  • Roadway resurfacing: complete
  • Roadway striping and sign/ delineator installation: ongoing, estimated completion by 10/25
  • Construction of intersection islands at the McAllister and Grove intersections: starting 10/25 estimated completion by 10/28

Questions? Please reach out to Julia.malmo@sfmta.com