For restoration of striping due to building construction:
- Download official striping plans from this webpage: https://www.sfmta.com/reports/striping-drawings
- If no striping record exists (eg alley or residential streets), then there isn’t a record and you have to prepare the drawing or take the measurements off the intersecting/main cross street
- Mark up and dimension work area to be restored. Refer to attached samples
- Provide photos of work area to be restored
- Immediately after paving, restore missing lane lines using temp tape (not paint)
- After completion of steps 1-4, SFMTA will prepare cost recovery invoice for SFMTA shops to conduct striping restoration. Allow at least one week for staff to review/prepare invoice.
- Upon receipt of payment and no further issues from SFMTA regarding striping or anything else, contractor will be directed to coordinate with SFPW-BSM inspector for final sign-off
- Contractor does not have to wait for SFMTA shops to complete striping restoration
Contact Information
Westley Myles