Construction Update
North Beach Utility Relocation
This week Central Subway crews continued to perform sewer construction and began work in the median of Columbus Avenue between Union and Powell streets.
Next week the contractor will restore the construction site. By the end of the day on Wednesday, the site will be paved, and all lanes will be reopened to traffic. In addition, the northbound bus stop on this block of Columbus Avenue will be open during regular service hours starting Thursday, November 22.
Central Subway crews will not be working in this area during the holiday season (Thanksgiving to New Year's Day); however, AT&T may be performing work related to the Central Subway in December. AT&T’s work will involve a crew of approximately two people working inside manholes to splice telephone connections. There will be no street excavation for this work.
During the holiday season, we will email construction updates as needed instead of once a week.
Should you have questions about construction or the Central Subway Project, don't hesitate to contact our team. You can reach us at central.subway@sfmta.com or by phone at 415-701-4371.
We appreciate your continued patience while construction is in progress.
-The Central Subway Team
Work Completed Nov. 12-16
This week the contractor performed sewer work and also worked in the median of Columbus Avenue.
Traffic impacts: To accommodate construction, the left lane for northbound traffic on Columbus Avenue between Union and Powell streets was closed during construction hours. On the southbound side of the street, the lanes were shifted to the west. Both southbound lanes remained open. In addition, the loading zone (yellow zone) on the south side of Union Street just west of Columbus Avenue was temporarily relocated around the corner, on Columbus Avenue, during construction hours.
Transit impacts: The northbound bus stop on Columbus Avenue at Union Street was closed during construction hours. The westbound bus stop on Union Street at Columbus Avenue was temporarily relocated to about 100 feet east of its regular location during construction hours.
Pedestrian impacts: Work was underway in the intersection of Columbus Avenue and Union Street, and the crosswalk crossing Columbus Avenue on the north side of the intersection was impacted.
Planned Construction Nov. 19-23
Next week the contractor will restore the construction site. This work involves backfilling excavations and paving the roadway. No construction will be in progress on Thanksgiving or Black Friday.
Traffic impacts: On Monday, the left lane for northbound traffic will be closed during construction hours. On Tuesday and Wednesday, the right lane for northbound traffic will be closed. Starting Thursday, all lanes will be open to traffic.
Transit impacts: The northbound bus stop on Columbus Avenue at Union Street will be closed during construction hours from Monday to Wednesday. The 30 Stockton and 8X/8BX Bayshore Express stop here. Starting Thursday, this bus stop will be reopened for regularly scheduled service. Also from Monday to Wednesday, the westbound bus stop on Union Street at Columbus Avenue will be temporarily relocated to about 100 feet east of its regular location during construction hours. The 39 Coit, 41 Union and 45 Union/Stockton stop here.
Pedestrian impacts: From Monday to Wednesday, work may be underway in the intersection of Columbus Avenue and Union Street, and the crosswalk crossing Columbus Avenue on the north side of the intersection may be impacted. Cones will be in place to designate a safe path of travel.