Details of Work to be performed:
L Taraval Improvement Project Update and Forecast
for the weeks of May 16 – May 28, 2022
Taraval Street - North
North side of Taraval between 37th to 26th avenues
5/5/22 – 5/16/22 Sewer line work from 32nd to 31st avenues
5/13/22 – 5/24/22 Sewer line work from 31st to 30th avenues
5/25/22 – 6/3/22 Sewer line work from 30th to 29th avenues
5/19/22 Sewer main inspections 26th to 20th avenues
North side of Taraval St. between 26th to 18th avenues
5/19/22 Sewer main inspections 19th to 18th avenues
East of 19th Ave.
5/5/22 – 6/3/22 Water line work by block from 15th to 19th avenues
5/16/22 – 6/3/22 Water line work at intersections of 15th, 16th, 17th and 18th avenues
6/6/22 anticipated Water line work, backfill and shoring at 19th Ave. and Taraval St. anticipated start
Taraval Street - South
South side between 35th to 22nd avenues
4/29/22 – 6/3/22 Sewer work by block from 32nd to 35th avenues
6/3/22 anticipated Sewer line work back fill and remove shoring at 22nd Ave. and Taraval St.
15th Ave. between Taraval and Ulloa streets
5/16/22 - 5/20/22 Excavation and connection east and west side of 15th Ave.
Ulloa Street
North side from 15th Ave. to Forest Side Ave.
5/20/22 – 6/3/22 Excavate, shore and connect on the north side of Ulloa St. between Forest Side Ave. to 15th Ave.
Temporary staging locations
4/25/22 – 5/20/22 18th Ave. west side from Taraval to Ulloa streets
Staging area is approximately 65 ft. long and 10 ft. wide
4/25/22 – 5/20/22 14th Ave. west side from Ulloa to Vicente streets
Staging area is 10 ft. wide and approximately 80 ft. long
4/28/22 – 6/3/22 35th Ave. west side from Taraval to Ulloa streets
Staging area is approximately 74 ft. long and 10 ft. wide
4/29/22 – 5/28/22 37th Ave. east side from Santiago to Rivera streets
Staging area is 250 ft. long and approximately 10 ft. wide
5/4/22 – 5/27/22 31st Ave. west side from Taraval to Santiago streets
Staging area is approximately 80 ft. long and 10 ft. wide
5/5/22 – 5/27/22 34th Ave. west side from Taraval to Santiago streets
Staging area is approximately 55 ft. long and 10 ft. wide
5/9/22 – 5/28/22 32nd Ave. west side from Taraval to Santiago streets
Staging area is approximately 75 ft. long and 10 ft. wide
5/8/22 – 6/6/22 36th Ave. west side from Taraval to Santiago streets
Staging area is approximately 220 ft. long and 10 ft. wide
5/12/22 – 6/10/22 17th Ave. west side from Taraval to Santiago streets
Staging area is 80 ft. long and approximately 10 ft. wide
Muni Service
L Shuttle Bus Provides service for the L Taraval line between Embarcadero Station and SF Zoo
L Taraval segment B construction has reached a phase where the rail tracks west of the intersection of Ulloa and Madrone streets have been taken offline to complete construction work. Work needs to be performed during construction to facilitate the reconstruction of the water and sewer mains as well as replace the tracks and overhead lines.
What to Expect:
New sewer and water lines
- During excavation and installation some driveways may be temporarily inaccessible
- Excavation requires jackhammering of the pavement. Dust control measures will be in place to prevent dust kick up from the work
- Heavy vibrations from the shoring and sheet piling work is expected for open trench work
Vehicle traffic
- Temporary lane closures east of intersections where work will be performed
Ulloa St. north side from 15th Ave. and Funston Ave.
East and west side of 15th Ave. between Taraval and Ulloa streets
- Posted no parking signs for the duration of work
- Access may be delayed accessing residence, crew will allow safe access during construction
- Sidewalk open for trenchwork
Temporary staging and construction areas
- Posting of no parking signs along the staging areas
- Posting of no parking signs in active construction areas
Time of Work:
Monday through Friday, from 8 a.m. to 5 p.m.
No weekend work
Traffic Impacts:
- Some parking will be temporarily restricted in construction zones
- Traffic lanes will be modified during active work
- There will be dedicated flagger(s) to direct traffic and pedestrians
- Temporarily close lanes at intersections with detours
Impacts from outside projects
Public Works 19th Ave.
Public Utilities Commission Vicente St., from Wawona St. to 34th Ave.
(PUC) Wawona St., 15th Ave., and on Vicente St. west of 19th Ave.
PGE
Gas line work
19th Ave. and Taraval St., intersection TBD
Taraval St. south side from 14th to 15th avenues
Intersections of 16th, 17th, 29th avenues
Taraval St. and 30th, 33rd and 36th avenues 6/3/2022 anticipated start
Anticipated – subject to change