Work Forecast Plan for the Weeks of October 5 to October 16, 2020
|
Details of Work Performed: |
- Continuation of waterline work is planned for:
- October 5-9 between 46th and 44th Avenue
- October 5-9 and October 12-13 between 44th and 43rd Avenue
- October 12-16 between 48th and 46th Avenue
- Track replacement work is planned for:
- October 5-9 and October 12-16 between 40th and 37th Avenue
- Starting Monday, October 12 between 46th and 43rd Avenue
- Installation of Muni overhead contact system (OCS) pole is planned for:
- October 8-9 at the northwest corner of 43rd Avenue and Taraval Street
- October 8-9 at the southwest corner of 41st Avenue and Taraval Street
- October 8-9 at the northeast and southeast corner of 48th Avenue and Taraval Street
- October 8-9 at the northwest corner of 47th Avenue and Taraval Street
- October 8-9 at the southwest corner of 46th Avenue and Taraval Street
- October 12-13 at the southeast corner of 46th Avenue and Vicente Street
- October 12-13 on 46th Avenue between Vicente and Wawona Street
- October 12-13 at the southwest corner of 46th Avenue and Wawona Street
- October 12-13 at the northwest and southwest corner of 47th Avenue and Wawona Street
- October 12-13 at the northeast corner of 46th Avenue and Vicente Street
- Transfer of guy wires from existing poles to new poles is planned for:
- October 12-13 between 48th and 46th Avenue from 10:00 p.m. to 6:00 a.m.
- Construction of replacement Muni overhead contact system (OCS) pole's foundation is planned for:
- October 5-7 at 47th Avenue and Wawona Street
- October 5-7 at 46th Avenue and Wawona Street
- October 9 and October 12 at the northwest corner of 46th Avenue and Wawona Street
- Removal of existing overhead contact system (OCS) wires is planned for:
- October 11-12 between 47th and 48th Avenue from 10:00 p.m. to 6:00 a.m.
- October 12-16 at 46th Avenue and Taraval Street
|
What to Expect: |
Excavation requires jackhammering of the pavement. Dust control measures will be in place to prevent dust kick up from the work.
Heavy vibrations from the shoring and sheet piling work is expected for open trench work.
|
Time of Work: |
- Monday to Friday 8:00 a.m to 5:00 p.m.; Saturday to Sunday 8:00 a.m to 5:00 p.m.
- Night work starting Sunday, October 11 to Thursday, November 19 from 10:00 p.m. to 6:00 a.m. Please refer to project forecast for indicated night work.
|
Traffic Impacts: |
Some parking will be temporarily restricted in construction zones and traffic lanes will be modified during active work.
For track replacement work, traffic will be detoured at the intersections of 38th, 39th, 40th, 44th, and 45th Avenue at all times of the day until track replacement work along these segments are complete. During active construction hours, parking on both sides of the blocks will be temporarily restricted to give the crew the safety clearance they need to demo and replace the aged tracks in the center of the road and allow eastbound/westbound vehicular traffic. Parking will be returned at the end of each work day along the impacted blocks.
|
|
|
The following two-week construction forecast is subject to change due to weather delays or unexpected field conditions.
Questions or concerns? Contact us at LTaravalProject@SFMTA.com or 415.646.2382
Stay Up To Date: For L Taraval Improvement Project work forecast and updates, please sign-up for email updates by visiting LTaravalProject/SFMTA.com.
☎ 311 (Outside SF 415.701.2311; TTY 415.701.2323) Free language assistance / 免費語言協助 / Ayuda gratis con el idioma / Бесплатная помощь переводчиков / Trợ giúp Thông dịch Miễn phí / Assistance linguistique gratuite / 無料の言語支援 / 무료 언어 지원 / Libreng tulong para sa wikang Filipino / การช่วยเหลือทางด้านภาษาโดยไม่เสียค่าใช้จ่าย / خط المساعدة المجاني على الرقم