Construction Update
Feb. 2-11, 2013
During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. No Central Subway construction is planned to occur in Chinatown or North Beach.
For descriptions of construction impacts in each neighborhood, scroll down or click on the links below. We also post construction, traffic detour and Muni impact information on our project Google Map.
Construction impacts are planned to change at these locations by February 11:
- Northern SoMa (Market to Harrison): New construction may commence on 4th Street between Market and Stevenson on Saturday, Feb. 9.
At these locations, current construction impacts are planned to continue until February 11:
- Southern SoMa (Harrison to King/Berry): Two lanes of traffic to remain open on 4th Street between Harrison and Bryant. Launch box construction to continue.
- Union Square: Foundation demolition and subsurface wall construction to continue on Stockton Street between Geary and Ellis. Ground improvement to continue on Ellis Street between Stockton and Powell.
- Chinatown: No construction planned
- North Beach: No construction planned
We appreciate your patience and support while we build this essential upgrade to San Francisco's public transportation system.
-The Central Subway Team
Crews are constructing a launch box beneath 4th Street, at the site where tunneling will begin. The ramp that will be used to access the launch box is shown here, on the right. Southern SoMa
4th Street from Harrison to King/Berry
On 4th Street between Harrison and Bryant streets, the contractor is constructing a major excavation known as a launch box at the site where tunneling will begin this year.
Planned construction:
- Install launch box supports
- Continue launch box excavation
Traffic and pedestrian impacts:
- The two lanes on the east side of the street (left lanes for southbound traffic) will remain open to vehicle traffic
- The on-ramp to westbound I-80 may be closed from 8 p.m. to 4 a.m. on weeknights and all day Saturday and Sunday
- The sidewalk on the west side of the block will remain closed; the sidewalk on the east side of the block will remain open
Traffic and pedestrian controls are in place. For more information on current construction impacts at this site, check out this blog post.
This week on 4th Street between Howard and Folsom, crews prepared this rebar cage for installation into a subsurface wall. Northern SoMa
4th Street from Market to Harrison
On 4th Street between Howard and Folsom streets, the contractor is constructing below-ground walls, called headwalls, at the site of the future Yerba Buena/Moscone Station. The walls will cross 4th Street at two points on this block. For more information on construction at this site, check out this blog post.
In addition, the contractor is performing ground improvement work (installation of compensation grout tubes) on 4th Street between Folsom and Harrison. More information is available in this construction notice.
The contractor may begin construction on 4th Street between Market and Stevenson on Saturday, February 9. The same equipment that will be used between Folsom and Harrison will be used at this location, and the start date may change based on the progress of utility potholing between Folsom and Harrison. For more information on construction at this site, check out this construction notice.
Planned construction (Market to Stevenson):
- Set up construction zone and pothole for utilities. This work may start Feb. 9.
- Pavement breaking is required for this work. Neighbors may experience a temporary increase in construction noise while pavement breaking is in progress.
Traffic and pedestrian impacts (Market to Stevenson):
- Two lanes on the eastern side of the street (near Ross) may be closed starting Saturday, Feb. 9
Planned construction (Howard to Folsom):
- Construction of southeast and northeast headwalls
- Construction of new water line
- Pavement breaking is required for this work. Neighbors may experience a temporary increase in construction noise while pavement breaking is in progress.
Traffic and pedestrian impacts (Howard to Folsom):
- At least two lanes of traffic on 4th Street will remain open at all times during the day. The block may be reduced to one lane on one night next week from 8 p.m. to 6 a.m. to allow for the installation of a rebar cage.
- Work will be underway on the eastern side of the block, with at least two lanes open on the western side of the block (right lanes for southbound traffic)
- The sidewalks will not be impacted
Planned construction (Folsom to Harrison):
- Pothole for utilities
- Construct trenches for ground improvements
- Pavement breaking is required for this work. Neighbors may experience a temporary increase in construction noise while pavement breaking is in progress.
Traffic and pedestrian impacts (Folsom to Harrison):
- One lane on the eastern side of the street (near Pacific Bicycle and Whole Foods) will be closed
This drill is being used to improve the ground at the site of the future Union Square/Market Street Station. Union Square
Stockton Street from Market to Post
On Stockton Street between Geary and Ellis streets, the contractor is installing below-ground walls called headwalls at the site of the future Union Square/Market Street Station. In addition, ground improvement is underway on Ellis Street between Stockton and Powell streets.
Planned construction:
- Remove abandoned utility pipe
- Demolish foundations on Stockton Street between O'Farrell and Geary (in front of Louis Vuitton). This work involves impact equipment and may temporarily increase construction noise in the area.
- Install shallow subsurface walls (guide walls), mobilize to install headwalls and commence headwall construction between Ellis and O'Farrell
- Install ground improvement (jet grouting) components
Traffic, transit and pedestrian impacts:
- Stockton Street between Geary and Ellis is closed to all vehicles except emergency vehicles
- Ellis Street between Stockton and the Ellis-O'Farrell Garage (between Stockton and Powell) is closed to westbound traffic
- The 38/38L Geary may experience delays around Union Square
- Sidewalks on Stockton Street between Ellis and Geary will remain open, but they may be narrowed to facilitate construction
More information about construction at this site is available in this construction notice and this press release.
This property on Washington Street is the future location of the Chinatown Station. Chinatown
Stockton Street from California to Broadway
No construction is planned to occur in Chinatown during the next 10 days.
No construction is planned in North Beach in the next 10 days. North Beach
Columbus Avenue from Union to Filbert
No construction is planned to occur in North Beach during the next 10 days.
Central Subway Construction Fast Facts
Project Alignment: 4th Street between Berry and Market streets; Stockton Street between Market Street and Columbus Avenue; Columbus Avenue between Stockton and Filbert streets.
Transit Reroutes: The southbound 8X/8AX/8BX Bayshore Express, 30 Stockton, 45 Union/Stockton and 91 Owl Muni bus routes have been rerouted to accommodate construction in Union Square and SoMa. These reroutes will remain in effect throughout the duration of Central Subway construction. More information is available online here.
Contact Us: Should you have questions about construction or the Central Subway Project, don't hesitate to contact our team. You can reach us at central.subway@sfmta.com or by phone at 415-701-4371.
For More Information: The Central Subway team posts frequent project updates on a variety of social media outlets. To find out more about the project and construction progress, follow us on Facebook, Twitter, Instagram or Flickr, and check out our blog.
Construction schedules are subject to change.