Crews made great progress on the Valencia Street Bikeway Improvements Project last week, accomplishing several important tasks on Valencia Street.
The SFMTA paint shop worked at a rapid pace and removed all center running bikeway intersection striping between 16th and 22nd streets. We also removed bike lane infrastructure all the way to 17th Street. Wet weather affected the grouting between 18th and 19th streets, so crews will need to regrout this area. Grouting keeps water out of the bottom of the street base, preventing future underground erosion and potholes.
This week, crews are scheduled to work on: removing bike lane infrastructure and grouting, as well as any necessarily touch-ups from rain impacts at the locations listed below.
Coming up: Paving
In two weeks, the center-running bike lane will be gone, and we will begin to pave the center of the street. Paving will require us to temporarily restrict some parking on Valencia to accommodate paving operations and related traffic routing around the work zone. During paving there may be noise and traffic impacts. Paving is anticipated to take about 1-2 days per block and about 3 weeks to complete the entire corridor. In next week’s update, we’ll share more details about paving work so that you can prepare.
Those traveling on the corridor are advised to stay alert and allow more travel time during construction. You may want to consider traveling on parallel streets during construction. Signage and flaggers will direct people on bikes and in cars.
The work listed below is scheduled for Monday through Friday, 9 a.m. to 6 p.m.
The following construction forecast is subject to change, including the possibility for work during the weekend. For more project details, please visit the Valencia Bikeway Improvements page. In case of emergencies during construction, please call 415.695.2134.
This week:
Monday through Friday, March 17-21
- Valencia between 18th and 19th streets Grouting
- Valencia between 17th and 18th streets Grouting
- Valencia between 16th and 17th streets Removal of bike lane infrastructure, grouting
- Valencia between 15th and 16th streets Removal of bike lane infrastructure
Planned for next week, subject to change:
Monday through Friday, March 24-28
- Valencia between 15th and 16th streets Removal of bike lane infrastructure, grouting
Shop Local!
Help support local businesses during construction! From shopping to food to nightlife, here are some ideas about how to spend a perfect day along Valencia Street.
Compre en los negocios del vecindario
¡Apoye a los negocios durante la obra! Haga sus compras, visite restaurantes y disfrute de la vida nocturna. Aquí tiene algunas ideas para pasar un día perfecto en la calle Valencia Street. |