This timeline includes all projects related to the J Church, including capital and service improvement projects. For additional information about a specific project, please see the project webpage.
2019 through 2021
Church and Market Streets Intersection Improvements
- Early outreach regarding pandemic-related changes to the Muni stop and service near the intersection.
Late 2022
- Targeted outreach to key community groups
Spring 2023
Church and Market Street Intersection Improvements
- Targeted outreach to merchants
- Continued outreach to key community groups
Summer 2023
Church and Market Street Intersection Improvements
- SFMTA Board action on southbound right turn restriction (except Muni) from Market Street to Church Street.
- Please note commercial vehicles and taxis will still be able to access southbound Church Street but must do so from Church Street north of Market Street.
- Proposal for approval of community-informed design to SFMTA Board
Fall 2023
- Legislation of project elements
2024
- Implementation of quick-build elements
-
Targeted outreach to merchants and key community groups
-
SFMTA works with Public Works on concept design of permanent transit plaza
- Targeted outreach to key community groups and legislation and implementation of new stop sign and Muni stop changes on Church Street
2025
- Outreach to key community-based organizations and the Noe Valley community to collaborate on potential proposals on Church Street from 22nd to 30th streets
2026
- Implementation of capital components for all capital projects related to the J Church
Timeline to be determined
Service improvements by adding historic street cars from Church/Duboce to Balboa Park
- Anticipated to add 15-minute service with combined 7.5-minute frequency on the surface of the J Church
- Implementation dependent on hiring and training operators