The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.
All night work is italicized below. The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.
Tentative schedule:
In the next two weeks crews are scheduled to work on sewer and water main installation, sidewalk replacement, installing a joint utility trench and street light conduits, and potholing for upcoming work.
Tuesday through Friday, February 19 through February 22
- Chestnut to Lombard Night work is scheduled Tuesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Lombard to Greenwich. Night work is scheduled Tuesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Greenwich to Filbert. Night work is scheduled Tuesday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Filbert to Union. Night work is also scheduled Tuesday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Union to Green. Night work is also scheduled Tuesday through Friday between the hours of 8:00 p.m. and 7:00 a.m.
- Green to Vallejo.
- Washington to Clay.
- Clay to Sacramento.
- Sacramento to California. *Intensive noise and vibration is expected on Friday, February 22.
- California to Pine. (Friday only) *Intensive noise and vibration is expected on Friday, February 22.
- Pine to Bush.
- Bush to Sutter. (Tuesday through Thursday only) Intensive noise and vibration is expected.
- Sutter to Post. (Tuesday through Thursday only) Intensive noise and vibration is expected.
- Post to Geary.
- Geary to O'Farrell.
- Ellis to Eddy. (Thursday and Friday only)
- Golden Gate to McAllister (Thursday and Friday only)
- McAllister to Grove.
- Grove to Hayes.
- Hayes to Fell.
- Fell to Market. Night work is scheduled Tuesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. *Intensive noise and vibration is expected.
- Market to Mission.
Monday through Friday, February 25 through March 1
- Lombard to Greenwich. (Wednesday through Friday only)
- Greenwhich to Filbert. (Tuesday through Friday only)
- Filbert to Union. (Monday and Tuesday only) Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Union to Green. (Monday and Tuesday only) Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Green to Vallejo. (Monday and Tuesday only)
- Vallejo to Broadway.
- Broadway to Pacific.
- Pacific to Jackson.
- Clay to Sacramento. Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Sacramento to California. *Intensive noise and vibration is expected. Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- California to Pine. *Intensive noise and vibration is expected.
- Bush to Sutter. Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Sutter to Post. Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Post to Geary.
- Geary to O'Farrell.
- Ellis to Eddy.
- Golden Gate to McAllister. Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- McAllister to Grove. (Tuesday through Thursday only.) Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Grove to Hayes.
- Hayes to Fell. (Tuesday through Thursday only)
- Fell to Market. (Tuesday through Friday only) Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. *Intensive noise and vibration is expected.
- Market to Mission.
*We are working on improving the format of our weekly construction forecasts. Please share your feedback with staff at VanNessBRT@SFMTA.com