The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.
The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.
Tentative schedule:
In the next two weeks crews are scheduled to work on sewer and water main installation, sidewalk replacement, installing a joint utility trench, and street light conduits and potholing for upcoming work.
Monday through Friday, December 10 through December 14
- Bay to Francisco (Monday through Thursday only)
- Chestnut to Lombard Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. Disruptive noise is expected. On Monday and Tuesday night, intensive noise and vibration is expected.
- Lombard to Greenwich Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. Disruptive noise is expected. On Monday and Tuesday night, intensive noise and vibration is expected.
- Union to Green
- Green to Vallejo
- Vallejo to Broadway
- Broadway to Pacific
- Pacific to Jackson
- Jackson to Washington
- Washington to Clay Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Clay to California (Thursday and Friday only) Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- California to Pine *Intensive noise and vibration is expected Thursday and Friday only. Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Pine to Bush Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. On the night of Monday, December 10, intensive noise is expected.
- Bush to Sutter Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. On the night of Monday, December 10, intensive noise is expected.
- Sutter to Post Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. On the night of Monday, December 10, intensive noise is expected.
- Post to Geary Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Geary to O'Farrell Night work is also scheduled Monday, December 10, between the hours of 8:00 p.m. and 7:00 a.m.
- O'Farrell to Ellis Night work is scheduled Monday, December 10, between the hours of 8:00 p.m. and 7:00 a.m.
- Turk to Golden Gate (Thursday and Friday only)
- McAllister to Grove (Crews are only scheduled to work until 12:00 p.m. Thursday and Friday)
- Grove to Hayes (Monday and Tuesday only)
- Hayes to Fell (Monday through Thursday only)
- Fell to Market (Friday only)
Monday through Friday, December 17 through December 21
- Lombard to Greenwich (Friday only)
- Greenwich to Filbert (Wednesday to Friday only)
- Filbert to Union
- Union to Green
- Washington to Clay
- Clay to Sacramento
- Sacramento to California
- California to Pine *Intensive noise and vibration is expected.
- Bush to Sutter Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Sutter to Post Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Post to Geary Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Geary to O'Farrell
- Golden Gate to Turk
- McAllister to Grove (Monday and Tuesday only)
- Hayes to Fell (Wednesday through Friday only)
- Fell to Market
*We are working on improving the format of our weekly construction forecasts. Please share your feedback with staff at VanNessBRT@SFMTA.com