The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess.
The night shift for construction is scheduled between the hours of 8:00 p.m. and 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.
Tentative schedule:
In the next two weeks crews are scheduled to work on sewer and water main installation, sidewalk replacement, installing a joint utility trench, street light conduits and potholing for upcoming work.
Monday through Friday, December 3 through December 7
- Bay to Francisco (Monday and Tuesday only)
- Chestnut to Lombard (Monday and Tuesday only) Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. Disruptive noise is expected. On the night of Friday, December 7, intensive noise is expected.
- Lombard to Greenwich (Monday and Tuesday only) Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. Disruptive noise is expected. On the night of Friday, December 7, intensive noise is expected.
- Filbert to Union
- Union to Green
- Green to Vallejo (Wednesday through Friday only)
- Vallejo to Broadway (Wednesday through Friday only)
- Broadway to Pacific (Wednesday through Friday only)
- Pacific to Jackson (Wednesday through Friday only)
- Jackson to Washington
- Washington to Clay
- Clay to California (Tuesday through Friday only)
- Bush to Sutter (Monday and Tuesday only) *Intensive noise and vibration is expected.
- Sutter to Post: Night work is scheduled Thursday and Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Post to Geary Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Geary to O'Farrell (Wednesday through Friday only) Night work is also scheduled Monday through Wednesday, between the hours of 8:00 p.m. and 7:00 a.m.
- McAllister to Grove
- Grove to Hayes
- Hayes to Fell (Thursday and Friday only)
- Fell to Market (Monday and Wednesday only)*Intensive noise and vibration is expected Monday, December 3. Night work is also scheduled Tuesday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
Monday through Friday, December 10 through December 14
- Chestnut to Lombard Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. Disruptive noise is expected.
- Lombard to Greenwich (Wednesday through Friday only) Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. Disruptive noise is expected.
- Greenwich to Filbert (Wednesday through Friday only)
- Filbert to Union
- Union to Green
- Jackson to Washington (Monday and Tuesday only)
- Washington to Clay (Monday and Tuesday only) Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Clay to Sacramento Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- California to Pine *Intensive noise and vibration is expected.
- Pine to Bush (Wednesday through Friday only) Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. On Monday, December 7, intensive noise is expected.
- Bush to Sutter Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. On Monday, December 7, intensive noise is expected.
- Sutter to Post Night work is scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m.
- Post to Geary Night work is scheduled Monday and Tuesday between the hours of 8:00 p.m. and 7:00 a.m.
- Geary to O'Farrell
- O'Farrell to Ellis Night work is scheduled Monday through Wednesday, between the hours of 8:00 p.m. and 7:00 a.m.
- Ellis to Eddy
- Eddy to Turk
- Golden Gate to Turk
- McAllister to Grove
- Hayes to Fell
- Fell to Market (Monday through Wednesday only) Night work is also scheduled Monday through Friday, between the hours of 8:00 p.m. and 7:00 a.m. Intensive noise and vibration is expected.
- Market to Mission (Thursday and Friday only) *Intensive noise and vibration is expected.
*We are working on improving the format of our weekly construction forecasts. Please share your feedback with staff at VanNessBRT@SFMTA.com